Delhi Metro Completes Janakpuri West – Palam Tunnels on Magenta Line

After the Hauz Khas to Panchsheel Park breakthrough I recently posted about (See: Delhi Metro TBM Makes a Breakthrough at Panchsheel Park Station on Magenta Line), I’ve got even bigger news!

The Delhi Metro’s contractor for contract CC-34 of Phase 3, a JV of Hindustan Construction Company (HCC) & Samsung, has completed tunneling both the twin tunnels from the Vikaspuri shaft to Palam station on the 36.98 km Magenta line. This 4.475 km section includes 8 breakthroughs made between Vikaspuri to Janakpuri West to Dabri Mor to Dashrathpuri to Palam stations.

Route from Janakpuri W to Palam in southwest Delhi - Courtesy DMRC - full full map

Route from Janakpuri W to Palam in southwest Delhi – Courtesy DMRC – full full map

Actual location of shaft & stations on this section of the Magenta line

Actual location of shaft & stations on this section of the Magenta line

In a PDF published on HCC’s website that confirms the completion of this section, HCC has announced the sale of their 4 TBMs that were used for tunneling this section. So if one of you is looking for a TBM machine, then this might be a good time to contact HCC. Details about the 4 TBMs:

Earth Pressure Balance Machines S36 & S37 (nicknamed Jantar and Mantar)
• Manufactured by Terratec
• Duration of use: S36 – July 2014 to August 2015 and S37 – June 2014 to August 2015

One of the Terratec TBMs used on CC34 - Photo Copyright HCC

One of the Terratec TBMs used for CC34 – Photo Copyright HCC

Earth Pressure Balance TBMs S495 & S496 (nicknamed Riddhi and Siddhi)
• Manufactured by Herrenknecht
• Duration of use: S495 – Dec 2013 to May 2015 and S496 – Feb 2014 to June 2015

One of the Herrenknecht TBMs used on CC34 - Photo Copyright HCC

One of the Herrenknecht TBMs used for CC34 – Photo Copyright HCC

Tunneling Background on CC-34 (Vikaspuri to Palam):

In early 2014, tunneling work started from the Janakpuri West station south towards the Dabri Mor station where TBMs Ridhi & Sidhi made a double breakthrough (one of the few in the world) on 5 August 2014. Check out a cool video of it here: [Video] Double Breakthrough at Delhi’s Dabri Mor. Around the same time, Jantar and Mantar started tunneling from the Vikaspuri shaft* and made a breakthrough at Janakpuri West station on September 8 2014 and October 7 2014 respectively.

* In Phase 4 of the Delhi Metro project, the Vikaspuri shaft (located adjacent to the Outer Ring Road – see on google maps) will be used to launch TBMs towards Paschim Vihar and beyond. This ensures that the busy Janakpuri West station area will not be excavated again.

This graphic shows the direction of tunneling by the four TBMs:

Direction of Tunneling on CC-34 - Courtesy: Tunnel Talk

Direction of Tunneling on CC-34 – Courtesy: Tunnel Talk

Following the 4 breakthroughs mentioned above, all 4 TBMs were then taken to the Dashrathpuri station and launched in opposite directions. Ridhi & Sidhi tunneled their way to Dabri Mor station and completed their breakthroughs in May 2015 and June 2015 respectively. Jantar & Mantar on the other hand tunneled towards the Palam station and made breakthroughs last month (August 2015), thus marking the end of tunneling on the section mandated by the CC-34 contract.

Breakthrough at Janakpuri West - Photo Copyright Tunnel Talk

Breakthrough at Janakpuri West – Photo Copyright Tunnel Talk

For more updates on the Delhi Metro, check out the Delhi section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *