Can DMRC Really Start Trials Between Kalkaji & Botanical Garden in July?

So earlier this month, the Delhi Metro Rail Corporation (DMRC) took the local media on a tour of its new Hyundai Rotem trains (see 15 brilliant images) at Mukundpur and announced some very interesting timeframes for starting trial runs on its 2 new Phase 3 lines – the 38.235 km Magenta and 58.596 km Pink lines.

Here’s part of the table reproduced & polished from the DMRC’s website:

Line Section Distance (km) Month
Magenta (#8) Botanical Garden – Kalkaji 13.5 July 2016
Magenta (#8) Terminal 1 IGI Airport – Janakpuri (W) 9.86 July 2016
Magenta (#8) Terminal 1 IGI Airport – Kalkaji 14.87 Sept 2016

For starters, even though all tunneling works between T1 IGI & Janakpuri were completed in 2015, starting trial runs in July 2016 will not be possible as 5 more breakthroughs followed by track-work, signalling and other assorted works are left on the T1 IGI – Kalkaji section which leads to the Kalindi Kunj Depot where the trains are housed. See a list of under construction (pending) tunnel sections here: TBM Makes Breakthrough at Delhi Metro’s Greater Kailash Station.

The DMRC is also aiming to start trials in July 2016 on the elevated Botanical Garden – Kalkaji section, which is considered to be the line’s low hanging fruit. That’s again something which would not be possible as critical civil works are pending at multiple places in Noida. Here’s a look at one of the sites at Amrapali Marg between the Botanical Garden and the Okhla Bird Sanctuary station.

Recent satellite imagery:

This section is under construction by SP Singla under contract cc-82 of the Phase 3 project. Here are some images shot this month:

BotanicalGarden3

Viaduct leading to Botanical Garden station – Photo Copyright: Sandeep Goyal

BotanicalGarden2

Concrete pour in progress on pier#75 just north of Amrapali Marg – Photo Copyright: Sandeep Goyal

BotanicalGarden4

2 gaps in the viaduct – Photo Copyright: Sandeep Goyal

There’s evidently quite some civil work to be completed here followed by track, electrical, signalling & telecommunications work. All those would need at least another 5 months to be completed. So, much like the DMRC’s claim of starting trials on the Pink line between Majlis Park & Lajpat Nagar in October while simultaneously agreeing that land acquisition issues have not yet been resolved, I consider the July 2016 timeframe for the Magenta line to be highly deceptive and not achievable at all.

For more updates on the Delhi Metro’s Phase 3, check out the Delhi section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

4 Responses to "Can DMRC Really Start Trials Between Kalkaji & Botanical Garden in July?"

  1. Siddharth says:

    Can’t the trains be hoisted directly on the tracks like it was done in case of Gurgaon metro for trials

    Reply
    • TMRG says:

      Hi, they wouldn’t have to do that as the Kalindi Kunj Depot is already connected to the line. The viaduct for the most part is complete in Delhi, so the DMRC might initially start trial runs from Kalindi Kunj to Okhla/Jamia and gradually extend it westward to Kalkaji and eastward to Botanical Garden.

      Reply
  2. Siddhant kumar says:

    But work on pink line’s indarprastha extension – shiv vihar section is progressing fastly trials can start in September from vinod nagar depot

    Reply