TBM S53 Makes a Breakthrough at Lucknow Metro’s Hazratganj Station

Tunnel Boring Machine S53 ‘Ganga’ on Tuesday evening made a successful breakthrough at Lucknow Metro Line-1’s Hazratganj Station a day after the “official” breakthrough by its sister machine TBM S52.

This Ø6.52m Terratec EPB TBM was commissioned from the Sachivalaya Station’s Bapu Bhawan Shaft in March 2017 and took only about 3 months to build the 780m up-line tunnel of the 22.88 km Line-1’s 3.44 km LKCC-06 underground section. The TBM arrived outside the Hazratganj Station’s box in mid-June, but the operator & contractor chose to delay its breakthrough to take place until after S52’s staged breakthrough.

As per Vinayak Deshpande, MD of Tata Projects, who interviewed with the TOI

Due to many heritage structures, the stretch was highly challenging. During last five months, this complex project was executed in one of the busiest areas with no disruption to the common man.

Underground section’s map – view Lucknow Metro map & information

Unlike TBM S52’s breakthrough the other day, no grand celebration or media event was held for S53’s breakthrough. Here are a couple images –

TBM S53 – Photo Copyright: Vivek

S52 and S53 – Photo Copyright: LMRCL

And here’s a video. For no logical reason, they chose to also rotate S52’s cutterhead –

With tunneling work completed between Sachivalaya & Hazratganj stations, there are now 4 tunneling drives (and breakthroughs) remaining. As per the official tunneling plan, the Tata – Gülermak JV will now dismantle both TBMs, retrieve their parts and reassemble them again at the Sachivalaya (State Secretariat) Station’s western-end to build twin 613m tunnels towards the Hussainganj Station. However, as per a follower’s comments here who might be connected with the project, they now plan to redeploy them from the Charbagh Ramp towards Hussainganj Station instead. Stay tuned to find out what’s next!

For more updates, check out the Lucknow section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "TBM S53 Makes a Breakthrough at Lucknow Metro’s Hazratganj Station"

  1. Manoj kumar kaushik says:

    If any requirement for civil engineer .please contact with me. Cont no. 9690923220

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Manoj kumar kaushik Cancel reply

Your email address will not be published. Required fields are marked *