1st Segment Launched for Pune Metro Project’s Viaduct

On the night of December 14, workers and engineers from NCC launched the first precast segment at Kharalwadi for building Pune Metro’s 31.25 km Phase 1 project. Similar to Nagpur Metro’s viaduct construction, this feat at pier P349 was accomplished using the underslung construction method with a mobile crane. Going forward, NCC will deploy and commission a launching gantry crane to launch segments for building the line’s viaduct.

The contract for this section was awarded to NCC in February 2017, and their scope includes the construction of the 10.795 km Reach-1 (PCMC – Range Hills) section of the 16.589 km Line-1. Reach 1 is being built on the median of the Old Mumbai – Pune Highway and will consist of 9 stations located at PCMC, Tukaram Nagar, Bhosari (Nashik Phata), Kasarwadi, Phugewadi, Dapodi, Bopodi, Khadki and Range Hills – which will all be built by the HCC – Al Fara’a JV.

PCMC – Range Hills section of Pune’s Line-1 – view Pune Metro map & info

Each segment has a length of 3m with a top width of 8.5m, bottom width of 3.5m and weighs approximately 37 MT. Like the segments cast in Nagpur, segments cast in Pune have also been integrated and cast along with a parapet wall (unique in Indian metros) to cut down construction time, transportation time and the purchase cost of separate casting molds.

Some images from Pune Metro’s Twitter handle

Video –

In early January 2018, engineers launched another segment on top of pier p348 –

As per a tweet by Pune Metro on February 4, till now “the foundation for 79 pillars, total 41 pillars and 12 Pillars cap are completed”. Here are some images of segments stacked up at NCC’s yard at Nashik Phata waiting to be transported on-site –

For more updates, check out the Pune section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "1st Segment Launched for Pune Metro Project’s Viaduct"

  1. Yash Mhadgut says:

    Using Precast segments means more delay. The work being carried out on Mumbai metro’s Line 7 using U-girders is very fast. I think they will achieve the mid-2019 target. Pune metro should have also used U-girders.

    Reply
    • Akhilesh says:

      It depend upon design. Length of u girder upto 22 m. But in segment u go upto 37 m. No of pier and all also effect in u girder….

      Reply
    • Rishav Mahapatra says:

      Nagpur metro is also using precast segments and it’s pretty fast . So not much of a difference .

      Reply