Hyderabad Metro Phase 1 – Information & Map

Menu: Construction Updates | Overview | Phase 1 Info | Phase 2 Info

Phase 1 Information

Construction of the 72 km Phase 1 of the Hyderabad Metro system began in April 2012. In mid 2016, the Nagole – Mettuguda (8 km) of the Red line and the Miyapur – SR Nagar (12 km) section of the Green line are expected to open.

This phase involves the construction of 3 new lines on standard gauge tracks:

#1 – Green line – Miyapur – L B Nagar – 29.87 km
#2 – Blue line – JBS – Falaknuma – 14.78 km
#3 – Red line – Nagole – Raidurg – 28 km

The embedded maps below can be zoomed into!

Key for map below: Phase 1 (Under Construction) | Phase 2  (Planned) 

List of Major Contractors

Contract Contractor
Concessionaire L&T Metro Rail Hyderabad
Operations & Maintenance Contractor Keolis
Owner’s Engineer (General Consultant) AECOM – Feedback Infra JV
Programme Manager Parsons Brinckerhoff
Independent Engineer Louis Berger Consulting
Independent Safety & RAMS Halcrow
Traffic Consultants LEA Associates
Financial Consultants Deloitte Touche Tohmatsu
Carbon Credits Consultant Ernst & Young
Detailed Design Engineer for 6 stations at Ameerpet, Parade Grounds, Mahatma Gandhi Bus Station, Panjagutta, Hi-Tech City, and Jubilee Hills Checkpost Mott MacDonald

 