Sohna Elevated Road – Information & Status Update

21.65 km Sohna Elevated Corridor project (NH 248A) in Haryana is an operational 6-lane access controlled expressway with a route alignment connecting Rajiv Chowk in Gurugram to KR Mangalam University in Sohna.

The project had a construction deadline of June 2022 and was inaugurated / opened to vehicles on July 11, 2022. In the future, it will serve as the northern terminal to the under construction 1350 km Delhi – Mumbai Expressway.

  • Total Estimated Cost: Rs. 1,466 crore
  • Length: 21.65 km
  • Lanes: 6 lanes + local lanes
  • Owner: National Highway Authority of India (NHAI)
  • Status: Completed
  • Completion Deadline: June 2022
  • Opened: July 11, 2022
  • Project Model: Engineering, Procurement & Construction (EPC)

Route Map

Source: Times of India (TOI)

Status Update: Opened

Here’s a video by Rajan Singh (RSLive) showing the expressway on its inauguration day (July 11, 2022):

Tenders & Contractors

Sohna Elevated Road project has been divided into 2 civil packages with a 24 month deadline.

PackageContractor
Package 1: Rajiv Chowk in Gurugram to Badshahpur (8.94 km)Oriental Structural Engineers (OSE)
Package 2: Badshahpur to K.R. Mangalam University in Sohna (12.71 km)H.G. Infra Engineering Ltd. (HGIEL)

Page last updated: July 8, 2024. Have a question or spot an error? Let me know here.