213.803 km Tharad – Ahmedabad Expressway by NHAI is a proposed 6/8 lane access-controlled highway with a route alignment entirely in Gujarat state.

This greenfield expressway will be developed under Bharatmala Pariyojna (BMP). The project’s feasibility report and Detailed Project Report (DPR) was prepared by Intercontinental Consultants and Technocrats Private Limited (ICT). Land acquisition for the project is under way.

  • Total Estimated Cost: Rs. 6000
  • Project’s Length: 213.803 km
  • Land Acquisition Required: 1744.42 hectares
  • Lanes: 6/8
  • RoW: 70m
  • Status: Bidding Underway
  • Deadline: Not Finalized
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Engineering, Procurement and Construction (EPC)

Route Map

This expressway will connect the under construction Amritsar – Jamnagar Economic Corridor at Tharad, close to the Gujarat – Rajasthan border, with the operational Ahmedabad – Vadodara Expressway south of Ahmedabad city.

An official PDF route map (slightly more detailed) of the project can be viewed here on the Environmental Clearance website.

Final alignment is shown in Red color:

Current Status

Land acquisition is underway. Tenders for the construction of 3 packages were invited in October 2022.

Tenders & Contractors

This section will be updated as more tender notices are published.

Package (Chainage)Status / Contractor
Package 1: Tharad to Khimana (Km 0.000 to Km 43.500)Bidding Underway
Package 2: Khimana to Diodarda (Km43.500 to Km 83.500)Bidding Underway
Package 3: Diodarda to Udalpur (Km 83.500 to Km 127.000)Bidding Underway
Package 4: Udalpur to Giyod (Km 127.000 to Km 173.500)Bidding Underway
Package 5: Giyod to Bhuval (Km 173.500 to Km 213.803)Bidding Underway