Tharad – Ahmedabad Expressway – Information & Status Update

213.803 km Tharad – Ahmedabad Expressway by NHAI is a proposed 6/8 lane access-controlled highway with a route alignment entirely in Gujarat state.

This greenfield expressway will be developed under Bharatmala Pariyojna (BMP). The project’s feasibility report and Detailed Project Report (DPR) was prepared by Intercontinental Consultants and Technocrats Private Limited (ICT). Land acquisition for the project has not yet started.

  • Total Estimated Cost: Rs. 6000
  • Project’s Length: 213.803 km
  • Land Acquisition Required: 1744.42 hectares
  • Lanes: 6/8
  • RoW: 70m
  • Status: Proposed
  • Deadline: Not Finalized
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Engineering, Procurement and Construction (EPC)

Route Map

This expressway will connect the under construction Amritsar – Jamnagar Economic Corridor at Tharad, close to the Gujarat – Rajasthan border, with the operational Ahmedabad – Vadodara Expressway south of Ahmedabad city.

An official PDF route map (slightly more detailed) of the project can be viewed here on the Environmental Clearance website.

Final alignment is shown in Red color:

Current Status

Land acquisition has not yet started. Tenders for construction have not yet been invited.

Tenders & Contractors

This section will be updated when tender notices for its construction are published. There will most likely be 4-5 packages.

Package (Distance)Contractor (Value)
TBDTBD
TBDTBD

Page last updated: October 3, 2022. Have a question or spot an error? Let me know here.