Bareilly-Gorakhpur Expressway – Information & Status

500 km Bareilly – Gorakhpur Expressway by NHAI is a proposed 4 lane access-controlled highway with a route alignment in Uttar Pradesh.

This greenfield expressway under Bharatmala Pariyojna (BMP) Phase 2 will run parallel to the Nepal Border. It’s part of the larger 900 km Shamli – Gorakhpur Expressway project. Land acquisition for its construction has not yet started.

The expressway is expected to be completed and opened in 2028. Its Detailed Project Report (DPR) has not been made available online by NHAI.

  • Total Estimated Cost: Rs. 26,486 crore
  • Project’s Length: 500 km
  • Lanes: 4
  • RoW: N/A
  • Status: DPR Preparation, Detailed Design
  • Land Acquisition Requirement: N/A
  • Deadline: N/A
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Engineering, Procurement and Construction (EPC)

Route Map

An official PDF route map will be added here when available with a village and district list.

The expressway will be connected to the Ludhiana – Bareilly Economic Corridor in the east and Gorakpur – Siliguri Expressway in the west.

Current Status

Land acquisition process for the expressway’s construction has not yet started. The project’s Detailed Project Report (DPR) is being finalized.

Tenders & Contractors

This section will be updated when tender notices for its construction are published.

Package & ChainageContractor (Value)
Scope UnknownTBD

Page last updated: December 27, 2023. Have a question or spot an error? Let me know here.