Odisha Capital Region Ring Road – Information & Status

110.87 km Odisha Capital Region Ring Road (CRRR) project by NHAI is an approved 6 lane access-controlled highway around Bhubaneswar and Cuttack, Odisha.

This 6 lane expressway will connect Rameswar in Khurda district with Tangi, with an aim to allow vehicles on national highway NH-16 to bypass Khordha town, Bhubaneswar, Athagarh town, Cuttack & Choudwar town.

CRRR’s alignment was finalized in April 2021. Land acquisition started in June 2022.. The project’s Detailed Project Report (DPR) is unavailable. Its foundation stone has not yet been laid.

  • Total Estimated Cost: Rs. 5,744 crore
  • Project’s Total Length: 110.87 km
  • Lanes: 6
  • Status: Land Acquisition & Bidding Underway
  • Deadline: N/A
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Engineering, Procurement, and Construction (EPC)

Route Map

A PDF route map will be added here when available.

CRRR’s alignment map via Government of Odisha

Tenders & Contractors

NHAI started inviting tenders (bids) for CRRR’s construction works in October 2022 with a 2 year construction deadline.

Package & ChainageStatus
Package 1: Design Km. 0.000 to Km. 40.700Bidding Underway
Package 2: Design CH.40.700 to 70.995 (village Bilipada to Gobindpur)Bidding Underway
Package 3: Gobindpur near Kuspangi (NH-42) to Tangi near Bandalo Toll Palza (NH-16) Design Km.70.540 to Km. 110.870Bidding Underway