Bangalore Airport Terminal 2 – Design & Status
Bengaluru’s Kempegowda International Airport is undergoing a major expansion project which will see a new Terminal 2 (T2) and a second runway (commissioned in 2019) in Devanahalli, Karnataka.
Terminal 2 is to developed in 2 phases to handle 25 million passengers per annum in Phase 1 and 45 million passengers per annum in Phase 2. It’s been designed by Skidmore, Owings & Merrill (SOM) architects and its civil construction contract was awarded to Larsen & Toubro with a value of approximately Rs. 3000 crore.
BIAL is also constructing Bengaluru Airport City on 463 acres of land surrounding the airport featuring a concert area, Retail, Dining and Entertainment (RDE) Village, business park, and 775 rooms in a combo hotel (managed by Ginger Vivanta).
Phase 1 Expansion
Phase 1 of Bangalore Airport’s Terminal 2 was inaugurated on November 11, 2022 by Prime Minister Narendra Modi. Domestic flights started operating on January 15, 2023 and international flights started operating on September 12, 2023.
- Estimated Cost: Rs 13,000 crore
- Built-up Area: 255,000 sq.m
- Opening (first flight): January 15, 2023
The project is founded on four pillars: technological leadership, the idea of a terminal in a garden, environmental and ecological stewardship, and a celebration of Karnataka’s rich heritage and culture.
The new terminal, unofficially called Garden Terminal will feature trees, small gardens and ponds with local species of plants. Passageways throughout the terminal will connect the passengers with nature. The ceiling at the entrance, check-in and security area will feature hanging planted bells.
The new terminal will also feature a large indoor garden with rammed-earth walls and waterfalls, which will act as a gateway into the densely-landscaped retail area. The three-storeyed forest belt is set to offer an unique outdoor experience for arriving and departing passengers. It will be well connected to the shopping area. The forest belt will be viewable from all main indoor spaces.
Kempegowda International Airport Terminal 2 expansion project includes a new multi-level car parking area and a multi-modal transport hub (MMTH) from where riders can board a Blue Line metro train (metro project’s Phase 2B) to connect to and from Bengaluru city.
Terminal Features
Processors | Phase 1 | Phase 2 |
Check-in Counters | 90 | 123 |
Security Check lanes | 22 | 40 |
Emigration Counters | 36 | 61 |
Immigration Counters | 60 | 113 |
Customs Hand bag inspection lanes | 9 | 14 |
Baggage Claim Belts | 9 | 16 |
Customs Red Lane Inspection Counters | 10 | 17 |
The project also consists of a CAT IIIB compliant runway, parallel taxiway, partial second parallel taxiway, runway connecting taxiways, taxiway links, cross field taxiways to connect to the existing airfield, partial second parallel taxiway to existing runway, Ground Service Equipment underpass, Eastern Access Underpass Tunnel, and the terminal T2 apron.
The Eastern Access Underpass Tunnel will be the first tunnel in the country open for vehicular traffic passing underneath an active taxiway.
Page last updated: June 28, 2024. Have a question or spot an error? Let me know here.