Madurai Metro – Information & Updates
Madurai Metro project is a mass rapid transit system (MRTS) proposed to be built in Madurai, Tamil Nadu by Chennai Metro Rail Ltd. (CMRL).
The project’s Detailed Feasibility Report (DFR) was prepared and submitted by Balaji Railroad Systems (BARSYL) to CMRL in November 2022. This report was forwarded to the Tamil Nadu state government in January 2023 for consideration.
The feasibility report suggested building a 31 km metro line between Thirumangalam – Othakadai with 20 stations and a train maintenance depot on a 45 acre site at Thirumangalam.
In February 2023, CMRL invited bids to prepare a Detailed Project Report (DPR) which is expected to be completed by December 2023.
Madurai Metro Deadline: To be Determined
Key Figures
Operational: 0 km | Under Construction: 0 km | Approved: 0 km | Proposed: 31 km
Route Map
Madurai Metro’s route has not been finalized. Exact details will emerge only after the DPR’s first draft is ready. An official PDF route map will be added here when available.
The 20 stations proposed in Madurai Metro will be tentatively built at Thirumangalam, Kappalur Toll Plaza, Dharmathupatti, Thoppur, Thirunagar, Thirupparankundram, Pasumalai, Vasantha Nagar, Madurai College, Madurai Junction Railway Station, Simmakkal, Keezhavasal, Therkuvasal, Goripalayam, Police Commissioner’s Office, K Pudur, Mattuthavani, Uthangudi, High Court Bench and Othakadai.
Tenders
Madurai Metro’s tenders aren’t yet available as the project has not been approved.
Major Contractors
Contract | Contractor |
Consultant for Preparation of Feasibility Study Report for introducing a Mass Rapid Transit System in Madurai city | Balaji Railroad Systems (BARSYL) |
Consultant for Preparation of Detailed Project Report (DPR) for Mass Rapid Transit System in Madurai | Aarvee Associates Architects Engineers & Consultants is lowest bidder |
Page last updated: October 19, 2024. Have a question or spot an error? Let me know here.