Sirhind – Sehna Expressway – Information & Status

108 km Sirhind – Sehna Expressway by NHAI is a proposed 6 lane access-controlled highway with a route alignment in Punjab connecting Fatehgarh Sahib and Sehna Khera via Malerkotla, Barnala and Bathinda.

This greenfield expressway under Bharatmala Pariyojna Phase II (Lot-9) will serve as an east-west expressway through southern Punjab. Land acquisition for the project started in December 2020.

The project’s Detailed Project Report (DPR) was prepared by Egis India Consulting Engineers and K & J Projects. Its pre-feasibility report’s PDF can be viewed here.

  • Total Estimated Cost: Rs. 4,733.58 crore
  • Project’s Length: 108 km
  • Lanes: 6
  • ROW: 60m
  • Status: Land Acquisition
  • Deadline: N/A
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Engineering, Procurement and Construction (EPC)

Design

Sirhind – Sehna Expressway will have:

  • Rail Overbridges: 1
  • Major Bridges: 2
  • Minor Bridges: 23
  • Vehicular Underpaas (VUP): 16
  • Light Vehicular Underpass (LVUP): 30
  • Interchanges: 8
  • Culverts: 135

Route Map

An official PDF route map will be added here when available.

The expressway will pass through 5 districts of Punjab: Fatehgarh Sahib, Patiala, Malerkotla, Sangrur and Barnala. An interchange will be built near Malerkotla to connect with the under construction Delhi – Amritsar – Katra Expressway.

Current Status

Land acquisition is underway. Bidding for construction has not yet started.

Tenders & Contractors

This section will be updated when tender notices for its construction are published.