Purvanchal Expressway – Information & Status

340.82 km Purvanchal Expressway project by UPEIDA is an operational 6 lane access-controlled road with a route alignment connecting Chand Sarai Village in Lucknow District with Haidaria Village in Ghazipur District.

This greenfield project was first announced in May 2015 as the Lucknow – Azamgarh – Ballia Expressway and land acquisition began soon after. Its foundation stone was laid by Prime Minister Narendra Modi in July 2018, and construction work started in October 2018 by 5 contractors on 8 civil packages.

Purvanchal Expressway was inaugurated and opened to traffic on November 16, 2021 with UPEIDA earlier chasing a May-end deadline.

  • Total Estimated Cost: Rs. 22,494 crore
  • Deadline: October 2021
  • Opened: November 16, 2021
  • Project’s Total Length: 340.824 km
  • Lanes: 6
  • Status: Under Construction
  • Owner: Uttar Pradesh Expressways Industrial Development Authority (UPEIDA)
  • Project Model: EPC (Engineering, Procurement and Construction)

Project Overview Video

Current Status

The expressway was inaugurated on November 16, 2021 by Prime Minister Narendra Modi.

Route Map

The expressway connects the districts of Lucknow, Barabanki, Sultanpur, Ayodhya, Ambedkar Nagar, Azamgarh, Mau, and Ghazipur.

The following not-so-pretty map from UPEIDA’s website shows the start and end points of the expressway. You’ll be better off following its alignment on Google Maps here.

An official PDF route map of Purvanchal Expressway will be added here when available.

Tenders & Contractors

The project has been divided into 8 civil packages with a 36 month deadline. Contracts allotted to 5 construction firms went into effect from October, 2018.

PackageContractor
PE-01: Chand Sarai (Dist. Lucknow) to Sansara (Dist. Barabanki) (Km 0+270 to Km 40+200Gayatri Projects
PE-02: Sansara (Dist. Barabanki) to Jaraikala (Dist. Amethi) (Km 40+200 to Km 79+900)Gayatri Projects
PE-03: Jaraikala (Dist. Amethi) to Sidhi Ganeshpur (Dist. Sultanpur) (Km 79+900 to Km 121+600)Apco Infratech
PE-04: Sidhi Ganeshpur (Dist. Sultanpur) to Sansarpur (Dist. Sultanpur) (Km 121+600 to Km 164+300)GR Infraprojects
PE-05: Sansarpur (Dist. Sultanpur) to Gobindpur (Dist. Azamgarh) (Km 164+300 to Km 218+300)PNC Infratech
PE-06: Gobindpur (Dist. Azamgarh) to Mojrapur (Dist. Azamgarh) (Km 218+300 to Km 246+500)PNC Infratech
PE-07: Mojrapur (Dist. Azamgarh) to Bijaura (Dist. Ghazipur) (Km 246+500 to Km 292+530)GR Infraprojects
PE-08: Bijaura (Dist. Ghazipur) to Haidariya (Dist. Ghazipur) (Km 292+530 to Km 340+500)Oriental Structural Engineering