93.2 km Kanpur Ring Road project by NHAI is an under construction 6 lane access-controlled highway in Kanpur, Uttar Pradesh, India.
The project’s foundation stone was by Nitin Gadkari on January 9, 2024. Its Detailed Project Report (DPR) is not available online.
This 6 lane expressway will be built via 5 packages and be connected to the under construction Lucknow – Kanpur Expressway. Its alignment will pass through Sachendi, Ramaipur, Rooma, Chakeri Airport, Trans Ganga City and Mandhana.
Land acquisition for Phase 1 started in north Kanpur (Chainage 0+000 to Km. 22+500) in September 2021.
- Total Estimated Cost: Rs. 5,182 crore
- Project’s Total Length: 93.209 km
- Lanes: 6
- Status: Under Construction & Bidding Underway
- Deadline: December 2027
- Owner: National Highways Authority of India (NHAI)
- Project Model: Engineering, Procurement, and Construction (EPC)
Route Map
A PDF route map will be added here when available.
Selected alignment of the project is shown in red below.
Tenders & Contractors
NHAI started inviting tenders (bids) for construction works in December 2022. This section will be updated when more tender notices are invited.
Package & Chainage | Status |
Package 1: Design Ch. 0.000 to Design Ch. 23.325 (Length: 23.325 km) | Raj Corporation Ltd. |
Package 2A: Design Ch.23.325 To Design Ch.32.090 Around Kanpur City (Length: 8.765 Kms) | 17 Firms Qualified |
Package 2B: Design Start from Ch.32.090 to Ch.51.200 around Kanpur city (Length: 19.110 kms) | Ajay Prakash Associates – S S Builders JV is lowest bidder |
Package 3: Design Ch. 51.200 to Design Ch. 68.650 (Length: 17.450 km) around Kanpur city and 4 lane Airport link Road (Length: 1.45 km) | Hillways Construction Company – Gour Road Tar Coat Pvt. Ltd. JV |
Package 4: Design Ch. 68.650 to Design Ch. 93.209 (Length: 24.559 km) | Raj Corporation Ltd. |
Page last updated: November 22, 2024. Have a question or spot an error? Let me know here.