2nd TBM Commissioned from Howrah Maidan for Kolkata’s Metro
Last week, the Afcons-Transtonnelstroy JV team in Kolkata commissioned their 2nd Tunnel Boring Machine at the Howrah Maidan station for building Kolkata Metro’s 16.34 km East-West line! The S639 TBM referred to as Rachna will build the down-line tunnel to the Howrah Junction railway station, and is trailing behind its sister machine, TBM Prerna, which has completed tunneling 147 meters out of the 550 meters for the parallel up-line tunnel on the same route.
At the time of writing this piece, Rachna has completed building 6 temporary rings and 4 permanent rings. Each ring is 1.4 meters wide.
Satellite view of Howrah Maidan station:
Some images of the TBM shot prior to its commissioning:
Here’s a look at the Howrah Junction railway station site where both TBMs will arrive in the 1st half of 2017:
The 9 km first phase of the line from Salt Lake Sector V to Sealdah is expected to be operational by mid 2018 while the 7 km second phase from Sealdah to Howrah which includes this tunnel section is expected to be operational in 2020.
For more updates, check out the Kolkata section of The Metro Rail Guy!
– TMRG
Both the TBMS wiil reach Howrah station in the first half of 2017, not 2018 as mentioned in your article.
In a previous article you had mentioned that the first TBM IS PRERANA not RACHANA.
Kindly clear this confusion and clarify the point.
Hi, thanks for pointing out those issues – I had corrected them within 2 hours of publishing. It should now reflect the correct info.
On a side note, I really need an editor to go through my posts. Always good to have a second pair of eyes 🙂
a nice initiative to get all the metro news in one page.
In this video (although in Bengali/ hindi) the project engineer maintained that if everything work properly within two months they will reach Howrah station within 2 months.
https://www.youtube.com/watch?feature=player_embedded&v=AJe_ekAbAvI
with best wishes
Shubhashis Rana
Hi, it’s doubtful that the 1st TBM will reach the Howrah Junction station in 2 months, but even if it did, then it’ll only make a breakthrough in 2017 as the TBM receiving shaft is still being prepared.
‘The first tunnel is expected to reach the river by October and Laldighi by next June, the official said.
The second tunnel is expected to reach Laldighi a month later.’
the project engineer
source: http://www.telegraphindia.com/1160713/jsp/calcutta/story_96389.jsp#.V4XZVTWli1F
Hi, the TBMs can reach the Howrah Jct station this year, but the shafts need to be prepared to receive them. I’ll share images of the shafts on Twitter whenever possible.
Thank you so much for such a prompt and encouraging reply from your side. I am really fortunate to express my opinions on your site.Hats off to each and every personnel associated with east west metro project for their untiring effort for the benefit of Kolkata citizens.
in my opinion as there is no hard rock in Bengal and soil is soft. The TBM will cross the hooghly river by 2016 end and By 2017 end it may reach upto sealdah ( howrah maidan to Sealdah 6 km).
Hi, Afcons’ package includes the tunnels only up to Esplanade. Tunneling underneath the Hooghly is expected to start in Q2 2017.
According to the same engineer mentioned above tbms are expected to reach hoogly in two months if all circumstances are right.
Yes it is true afcons will dig till esplanade or even less till b.b.d bag according to earlier reports tunnel digging till b.b.d bag will be complete by June 2017
According to reports in today’s Times of India Tbm prerna has covered 225 m and will reach Howrah station by first week of August and hooghly by October and Lal dighi by June next year and Tbm rachna will reach Lal dighi in July or
november
Hi, these are all tentative dates. The TBMs might reach Howrah Jct by those months, but if the shaft is not ready (which it won’t be until 2017), then how will the TBMs make a breakthrough and get ready to bore under the Hooghly?
Similarly, land acquisition is not yet entirely complete for a shaft at Strand Road or the Mahakaran/Lal Dighi/Dalhousie station – see this article. Without that being completed, the contractor will not begin tunneling onward from Howrah Junction.
it seems the tunnels will be completed well in advance but stations at dalhousie and esplanade will not be ready. According to reports stations will require at least 4 years from the date they get permission from national monument authority of india and army because of their depths.