GRIL & Krishna Win Amritsar-Bathinda Expressway’s Construction
September 23 Update: NHAI has issued contract LOAs to GR Infraprojects and Krishna Constructions
July 29 Original Post: GR Infraprojects and Krishna Constructions on Wednesday emerged as the lowest bidders for the 154.8 km Amritsar – Bathinda Expressway’s construction contract after National Highway Authority of India (NHAI) opened financial bids.
This 6 lane access-controlled highway (NH-754A) forms the northern part of the 1256 km Amritsar – Jamnagar Economic Corridor (NH-754 / EC-3). It was earlier planned as a 196 km brownfield upgrade of NH-54, but changed to a greenfield alignment in 2020.
NHAI invited bids for its 3 packages back in January 2021 – each with a 2 year construction deadline. Technical bids were opened in June to reveal 13 bidders had submitted a total of 34 bids.
Package 1
Scope: Development of 6-lane Amritsar-Bathinda greenfield section of NH-754A from village Tiba on NE-5A to junction with Moga Jalandhar Road (NH-703) near Dharmkot (from km 0+000 to 39+000) as a part of Amritsar-Jamnagar Economic Corridor in the state of Punjab on Hybrid Annuity Mode under Bharatmala Pariyojana Phase-I (Package-1)
- Length: 39 km
- NHAI’s Estimate: Rs. 772.50 crore
Financial Bid Values of Lowest 5 Technically-Qualified Bidders:
Firm | Bid (Rs. Crore) |
GR Infraprojects | 878.60 |
Chetak Enteprises | 892.44 |
Krishna Constructions | 916.56 |
Megha Engineering and Infra | 965.38 |
HG Infra | 992.41 |
Package 2
Scope: Development of 6-land Amritsar-Bathinda greenfield section of NH-754A from Junction with Moga Jalaandhar Road (NH-703) near Dharmkot to Junction withBhata Bhai Ka-Bhadaur Road near Dyalpura Bhai Ka (from 39+000 to km 93+000) as a part of Amritsar-Jamnagar Economic Corridor in the state of Punjab on Hybriad Annuity Mode under Bharatmala Pariyojana Phase-I (Package-2)
- Length: 54 km
- Estimate: Rs. 1075.59 crore
Financial Bid Values of Lowest 5 Technically-Qualified Bidders:
Firm | Bid (Rs. Crore) |
Krishna Constructions | 1176.66 |
GR Infraprojects | 1187.79 |
Gawar Constructions | 1189.84 |
Chetak Enterprises | 1221.31 |
Megha Engineering and Infra | 1247.44 |
Package 3
Scope: Development of 6-land Amritsar-Bathinda greenfield section of NH-754A from junction with Bhagta Bhai K-Bhadaur Road near Dyalpura Bhai Ka to Junction with Mandi Dabwali Bathinda Road on Nh-54 near Sangat Kalan (from km 93+000 to 154+866) as a part of Amritsar-Jamnagar Economic Corridor in the state of Punjab on Hybriad Annuity Mode under Bharatmala Pariyojana Phase-I (Package-3)
- Length: 61.866 Km
- Estimate: Rs. 1188.95 crore
Financial Bid Values of Lowest 5 Technically-Qualified Bidders:
Firm | Bid (Rs. Crore) |
Krishna Constructions | 1289.78 |
GR Infraprojects | 1324.27 |
Chetak Enterprises | 1348.79 |
Gawar Constructions | 1364.65 |
Megha Engineering and Infra | 1376.87 |
Amritsar – Bathinda greenfield expressway’s alignment is shown in dark blue (view large) below. Its northern terminal will be at Tiba village on the Amritsar-Nakodar spur of the Delhi-Amritsar Expressway
GRIL and Krishna’s lowest bids were 13.72%, 9.39% and 8.48% respectively higher than NHAI’s budgeted estimate, which I believe is within NHAI’s acceptable limits. Following possible negotiations, contracts can be expected to be awarded in the coming weeks with ground work starting as soon as October.
North of Bathinda, an interchange will be built near Rampura Phul to connect with the upcoming 75.5 km Ludhiana – Bathinda Expressway (NH-754AD) shown in red color above. Technical bids for that project’s Package 1 were opened in early July to reveal 13 bidders, while technical bids for Package 2 are currently planned to be opened on August 3. Stayed tuned…
For more updates, check out the Expressways section or my Home Page!
– TMRG
Too many expressways coming up in India (which is great!)
Can you please have a map of India with the expressway routes (like you have for metros)? Thanks!
https://i.redd.it/kqo70zvnn3z61.jpg
That’s a great map!
Don’t have the bandwidth to make a map right now. The one linked above by ANS is brilliant.
https://bit.ly/3xaTj1z
https://twitter.com/cbdhage/status/1421408911874314246 Pune Metro Rolling Stock Dispatched from Italy.
Hame piling work ki requirement hain TMR machine n hydraulic rig k liye pls send company’s contact number n mail
Siya Ram Piling Company P.C.YADAV [email protected]
Cont. 9314607777, 9664263366
khodiyar tractors
contact for constructon equipment hiring like moter grader , crane etc
9864191919
Mai bathinda k pass rehta hu mai apne khet mai se mitti outhana chahta hu je road k leye mitti cha he ae to plz canned me
Mai bathinda k pass rehta hu mai apne khet mai se mitti outhana chahta hu je road k leye mitti cha he ae to plz cal me 9814693090
I am Zakir Husain diploma Civil Engi 4 years experience bridge work I need job bridge line
We are manufacturer of all types of Road Signage /Safety Signage/Safety Policies Etc. If anyone interested , just contact with us.
We are repairing of all types of D,G sets 5 KVA to 500 KVA as well giving service of rented. No 6284450489 , adress KMG fules dabwali road near sangat kanchiya.
Shri Balaji borewell and construction company
We are working all types pilling and structured
Plz contact me 9414357325 7838956848
Shri Balaji borewell and construction company
We are working all types pilling and structured
Plz contact me 9414357325 7838956848
Manufacturer and supplier of bearings, Expansion Joints & Rebar Couplers. If interested please send your query on [email protected]
Hi
My name is Vikrant Sharma and i work in Crompton Lighting, we are manufacturers Pole, Lights, High mast and even we can do SITC work, We have a design team who can help to give you the exact calculation of lights, pole and lux required by NHAI.
Please free to contact me
9217173931