IL&FS wins Bangalore Metro contract
This contract involves the construction of a roughly 3.9 km long elevated viaduct from Mysore road station to Pattanagere station, including four elevated metro stations at Nayandahalli, Ajarajeshwari Nagar Station, Jnanabharathi Station and Pattanagere. This extension is part of the Purple line’s western extension to Kengri. As per the statement filed with the BSE, the civil work is to be completed in 27 months from the date of issue of letter of acceptance.
– TMRG