Excavation Begins for Delhi Metro’s Rameshwar Nagar Mid-Shaft

With piling works coming to an end, last week workers from the CEC-CICI JV began excavating soil for a crucial mid-shaft for package CC-04 of Delhi Metro’s 58.596 km Pink Line to facilitate the retrieval of 4 tunnel boring machines (TBMs) in north Delhi’s Rameshwar Nagar!

In some circles, this mid-shaft is also known as the ‘Gurudwara Shaft’ as it’s just down the road from Model Town’s R Block Gurudwara. It wasn’t part of the original construction plan, but had to be constructed as two TBMs commissioned from Azadpur station towards Majlis Park, tasked with tunneling 1100m, got stuck mid-way in 2014. Here’s a excerpt on the issue from the Tunnels and Tunneling magazine with a brief history of the difficulties faced and what CEC-CICI tried to do to resolve:

Both TBMs met with a large mass of intact rock which infringed the lower portion of the tunnel face and extended for approximately 30m. The TBMs used were both soft ground machines which have been used on a previous phase of the metro, and experienced high torque and overheating when attempting to cut through the rock zone. An attempt was made to break up the rock ahead of the cutter face by drilling and placing an expanding chemical to burst the rock and allow the cutter head to rotate and advance one ring at a time. The space within the chamber available to manage this exercise was very limited and matters were made worse by the presence of wet running sand above the rock zone which dictated working under compressed air.

In 2015, the CEC-CICI team secured a deal with HCC-Samsung (CC-34 project on Magenta Line) to lease 2 TBMs which they commissioned from the Majlis Park side in March & April 2016. View details & images:

  1. 1st Rescue TBM Commissioned for Delhi Metro’s Pink Line

  2. Last TBM Commissioned for Delhi Metro’s Pink Line at Majlis Park
Northern section of Delhi Metro's Pink line

CC-04 between Shalimar Bagh & Majlis Park – view Delhi Metro Phase 3 map & information

View from a rolling gantry crane - Photo Copyright: Dhiraj Kumar Singh

View from a rolling gantry crane – Photo Copyright: name removed by request

Three TBMs are sitting on either side of the shaft right now. This includes the original 2 TBMs on the south-side and the 1st ‘rescue’ TBM on the north-side. The 2nd ‘rescue’ TBM is expected to arrive here in early July. Once the entire shaft is excavated in about 45 days, then workers will descend into it and begin core cutting activities to push, dismantle & retrieve the 4 TBMs one by one.

For more updates, check out Delhi section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

13 Responses to "Excavation Begins for Delhi Metro’s Rameshwar Nagar Mid-Shaft"

  1. Siddhant Kumar says:

    Is the work is also stopped over nh 24 that is between east vinod nagar and patparganj there the pink line is going from patparganj to east vinod nagar piers are already erected from months.

    Reply
  2. Siddhant Kumar says:

    Please do a post whenever in any month work of viaduct starts over trilokpuri block 15 and mayapuri and punjabi bagh also.

    Reply
  3. Siddhant Kumar says:

    Is the work also stopped over nh24 . Piers are already erected.

    Reply
  4. Siddhant Kumar says:

    Is the work also atopped over nh 24. Piers are already erected.

    Reply
  5. Rajesh Gupta says:

    Rameshwar Nagar Mid shaft is also known as ‘Gurudwara shaft’ because there was Gurudwara at the site which was demolished for making way for shaft.

    Reply
  6. Shripad says:

    What s the difference in types/make of TBMs used by Delhi Metro in comparison with those at Bangalore ?

    Reply
    • TMRG says:

      Bangalore’s contractors deployed 2 different types of TBMs – Slurry & Earth Pressure Balance Machine (EPBM) while Delhi’s contractors have only used EPBMs. Their diameters are similar at 6.4m (despite different traction 3rd Rail vs OHE). The cutterheads (face) of the TBMs are always tailored to the requirements of the project.

      Reply
  7. Aishwarye says:

    Hi!, can you please tell me the work left in the opening up of violet line’s ITO – Kashmere Gate stretch and where exactly will the violet line interchange at kashmere gate, because we already have a yellow line going through the underground part?

    Reply
    • TMRG says:

      Lots pending. Station finishing, civil work for covering shafts & building entry/exit gates, track-laying work is left. The new station box is to the east of the Yellow Line’s station box, so you should be able to easily interchange from within the platform just how it’s done at Central Secretariat (Yellow< ->Violet).

      Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *