Two months after inviting bids from infrastructure companies for the construction of Reach 4’s 8.15 km viaduct, the Nagpur Metro Rail Corporation Ltd. (NMRCL) has now invited bids for the construction of 8 elevated stations between Sitabuldi & Prajapati Nagar in east Nagpur. This section is part of the 18.557 km east-west line and overall the 3rd of 4 sections where construction will start, with work already underway at Reach 1 (Sitabuldi-Khapri) and Reach 3 (Sitabuldi-Lokmanya Nagar).

A major part of the line will be built on the congested Central Avenue where 8 new stations are planned to come at Nagpur Railway Station, Dosar Vaisya Square, Agrasen Square, Chittaroli Square, Telephone Exchange, Ambedkar Square, Vaishnao Devi Square & Prajapati Nagar.

Notice Inviting Tenders link
CONSTRUCTION OF EIGHT NUMBER OF ELEVATED METJlO STATIONS VIZ PRAJAPATI NAGAR , VAISHNO DEVI SQUARE , AMBEDKAR SQUARE , TELEPHNE EXCHANGE. CHITIAR Oll SQUARE. , , AGRASEN SQUARE, DOSAR VAISYA SQUARE & NAGPUR RAILWAY STATION ON THE EAST-WEST CORRIDOR (REACH-4) OF NAGPUR METRPO RAil PROJECT

nagpurmetroreach4

Reach 4 between Sitabuldi & Prajapati Nagar – view Nagpur Metro information & map

NMRCL has estimated this contract to cost Rs. 180 crore. The last date for submitting tender documents for bidding is 4 pm on February 21, 2017 after which the bids will be opened & evaluated for eligibility at 4:30 pm. The financial bids are expected to be opened in Q2 2017 and once the contract is finalized, piling work for the stations can be expected to begin in Q3 2017.

Phase 1’s Status

Here’s a recap of Nagpur Metro’s status:

Green: Under Construction | Red: Bids Invited | Black: Bids Yet to be Invited

nagpurstatus1

January 23 Status of Nagpur’s Metro – view Nagpur Metro information & map

The NMRCL recently released the final design for the Sitabuldi Interchange Station prepared by a consortium of Enia Architects, Mahendra Raj Consultants and Worxpace Consulting. Hopefully bids for it will be invited soon, otherwise the NMRCL will have to run inefficient operations through 2 fragmented lines (shown in green above) like in Bangalore.

For more updates, check out the Nagpur section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

2 Responses to "Nagpur Metro Invites Bids for 8 Stations on East-West Line"

  1. S_A says:

    “The financial bids are expected to be opened in Q2 2016 and once the contract is finalized, piling work for the stations can be expected to begin in Q3 2017”

    Hey, isn’t year 2017? Q2 2016 has passed and opening of bids can’t be “expected” in 2016!