History of Chennai Metro’s Koyambedu – Nehru Park Section
With less than 24 hours to go for the inauguration of Chennai Metro’s 8 km Koyambedu – Nehru Park underground section of the 22 km Green Line, here’s a post with some high level information on the line’s history with a bunch of images. I’ve divided its timeline up into 3 distinct periods which’ll help demonstrate how much time was spent on each activity.
This section was originally scheduled to open in April 2015 and consists of two civil packages:
• UAA-04 – Shenoy Nagar – Egmore (4.47 km with about 3,350m twin tunnels)
• UAA-05 – Thirumangalam Ramp – Shenoy Nagar (4.90 km with about 3,370m twin tunnels)
Pre-Tunneling Period (2009-2011)
September 2009 – Chennai Metro Rail Ltd invited global bids for all 5 underground packages of Phase 1 (UAA-01 through UAA-05)
December 2010 – Package UAA-04 (Shenoy Nagar – Egmore) was awarded to L&T-SUCG JV with a contract value of Rs. 930.80 crores, while Package UAA-05 was awarded to the Afcons–Transtonnelstroy JV with a contract value of Rs. 1031.00 crores.
Tunneling Period (2011-2015)
• For UAA-04, L&T-SUCG JV procured & deployed 3 TBMs to make 6 breakthroughs (+2 breakthroughs on the upcoming Nehru Park – Egmore section):
TBM-1: STEC
TBM-2: STEC
TBM-3: Hitachi
The TBMs were initially deployed in 2012 to construct the upcoming Nehru Park – Egmore stretch, and then redeployed one after the other in mid-2013 in different directions from their launch shaft at Pachaiyappa’s College.
• For UAA-05, Afcons–Transtonnelstroy JV procured & deployed 2 TBMs to make 8 breakthroughs:
TBM-1: Herrenknecht (S718)
TBM-2: Herrenknecht (S717)
Both were launched one after the other in January and March 2013 from their launch shaft at Shenoy Nagar towards the Thirumangalam Ramp.
Timeline:
• May 30, 2013 – Afcons-TTS JV’s TBM-1 arrived at Anna Nagar East from Shenoy Nagar
• September 21, 2013 – Afcons-TTS JV’s TBM-2 arrived at Anna Nagar East from Shenoy Nagar
• January 21, 2014 – Afcons-TTS JV’s TBM-1 arrived at Anna Nagar Tower from Anna Nagar East:
• February 19, 2014 – Afcons-TTS JV’s TBM-2 arrived at Anna Nagar Tower from Anna Nagar East:
• June 24, 2014 – L&T-SUCG JV’s TBM-3 arrived at Kilpauk from Pachaiyappa’s College:
• July 15, 2014 – Afcons-TTS JV’s TBM-1 arrived at Thirumangalam from Anna Nagar Tower:
• July 19, 2014 – L&T-SUCG JV’s TBM-2 arrived at Kilpauk from Pachaiyappa’s College:
• August 25, 2014– Afcons-TTS JV’s TBM 2 arrived at Thirumangalam from Anna Nagar Tower:
• October 24, 2014 – Afcons-TTS JV’s TBM-1 arrived at the Thirumangalam Ramp from Thirumangalam Station:
• November 1, 2014 – L&T-SUCG JV’s TBM-1 arrived at Shenoy Nagar from Pachaiyappa’s College:
• December 16, 2014 – Final TBM breakthrough of UAA-05 by Afcons-TTS JV’s TBM-2 at the Thirumangalam Ramp from Thirumangalam Station:
• February 2, 2015 – L&T-SUCG JV’s TBM-3 arrived at Nehru Park from Kilpauk:
•February 2, 2015 – L&T-SUCG JV’s TBM-2 arrived at Shenoy Nagar from Pachaiyappa’s College:
• April 21, 2015 – Final TBM breakthrough of UAA-04 by L&T-SUCG JV’s TBM-1 at Nehru Park from Kilpauk:
Post-Tunneling Period (2015-2017)
Track-laying work started at the Thirumangalam Ramp in December 2014 and Platform Screen Door (PSD) installation in April 2016.
On the train testing side of things – in October 2015, CMRL operated an OHE Wagon up to Anna Nagar Tower Station after electrification on a 2 km section was completed. CMRL launched trial runs between Koyambedu & Anna Nagar East stations in April 2016, extended them to Shenoy Nagar in July 2016 and finally to Nehru Park in October 2016. The line was certified fit for commercial operations by the Commissioner of Metro Rail Safety (CMRS) in mid-April after a 2-day safety inspection on April 12-13.
Did I miss out on anything? Looking forward to the line’s inauguration at 10 am tomorrow! 😀
For more updates, check out the Chennai section of The Metro Rail Guy!
– TMRG
Hey, Do write a similar post about the heritge line when it opens next month..It will be good to read considering that a lot has happened for the completion of that line
Is that the Delhi metro heritage line?
Will do! Since starting this site, I’ve written one other such post on Bangalore’s EW line – check it out here.
Awesome recap! Also, point out if there is any genuine reason for tunneling delay, such as hard rock or loose soil etc.
Thanks! From what I know, all TBMs used for this section were configured for soft ground/soil. Tunneling related delays were minimal – I think the pre-tunneling (resource & TBM mobilization) & post-tunneling period dragged the project on for a little longer than it should have.
What is the procurement cost for a single TBM? I feel like if the contractors used double the number of TBMs they could have probably finished it in time but I guess the cost factor prevents that. Do they mention how many TBMs are they planning to use while bidding for a stretch?
So lets assume during bidding stage another contractor bids for the same stretch but it plans to use double the number of TBMs (without knowing how many TBMs are their competitors gonna deploy) so their bid will be higher and will not get chosen but then there will be a higher probability of them finishing the project in time. So how’s the decision made then? Do they always choose the lower bid or they consider the time factor too?
While awarding the contract does the respective metro rail authority specify the number of TBMs that should be used or any limit is imposed on the number of TBMs to be used?
Also, is there a fine for not completing the work in time?
I know, stupid questions but just curious.
Hi, there are no stupid questions!
Metro operators indeed specify the minimum number, type and quality (new/refurbished) TBMs at the time of bidding which the contractor must abide by. Contractors can always deploy more TBMs to finish work before time, but there’s usually no incentive to do so.
A new 6.6 dia EPB TBM costs anywhere from Rs. 30-50 crores, and really depends on its configuration (single shield, multi-shield, slurry-shield), thrust and brand. The cost of leasing one is typically around Rs. 80 lakh-1 crore per month.
I haven’t heard of any fines ever being imposed. Operators don’t go down that route as doing so during the course of construction might put that entire section on-hold.
Hi TMRG,
Given you have all the dates of launch and end, can you put together a quick summary of the average tunneling speed (in metres/week or metres/month) in various metro projects in India, excluding extended periods of repair and damage?
Hi, there’s a serious gap in progress reporting by contractors and operators. I just don’t have exact launch dates, exact tunnel distances to the meter or the progress available at this time.
Hi TMRG,
Nice compilation of facts. However, there is a slight date issue in this line for UAA-04, “All 3 were launched one after the other in mid-2013 in different directions from their launch shaft at Pachaiyappa’s College.” The TBM’s for UAA-04 were launched from Nehru Park launching shaft initially. Pachaiyappa college shaft was not ready by that time. There were some protests there. Also the first drive was in mid 2012. I was the planner at that site then.
Thanks for the compilation. It gives a great picture altogether.
Thanks,
Albert
Hi Albert – Thanks for the input! My post was strictly to document the new section and doesn’t include the Nehru Park – Egmore drives. But I’ll go ahead and modify the text to make UAA-04’s timeline a little clearer.
hello,
I would like to know what are those here standing towers with louvers on all the face, in the Chennai under group metro stations. I’m trying to find what these are but unable to sort it. please let me know about this, and also can u share any in depth details about Nehru park metro station, including if any plan by any chance. as I’m doing a final year thesis this would help me in design purpose.
thanking you