Longjian–KEC Begins Piling for Delhi Metro Line-7’s Extension
Following a small puja, workers and engineers from Longjian – KEC JV today officially began piling work for the construction of a 12.558 km extension of Delhi Metro’s Pink Line (Line-7) between Maujpur and Majlis Park.
Piling work commenced this afternoon for pier P274 in Delhi’s Wazirabad neighborhood situated on the western bank of the Yamuna River. On the eastern bank, workers had last week bored a test pile for its 560 meter long bridge over the river.
Longjian – KEC JV was awarded Delhi Metro Phase 4’s second contract for Package DC-02 (Maujpur – Sonia Vihar – Majlis Park) in November 2019 with a contract value of Rs. 1,080 crore and completion period of 30 months.
Their scope of work includes building the line’s 12.558 km viaduct, bridge over the Yamuna River, a PWD double-decker flyover and 8 stations at Yamuna Vihar, Bhajanpura, Khajuri Khas, Sonia Vihar, Wazirabad Surghat, Jagatpur Village, Jharoda Majra and Burari.
Here are a couple snaps from the Wazirabad site:
And here’s a snap shot on June 13 showing more test piling work underway on what looks like the approach road to the Signature Bridge:
For more updates, check out the Delhi section of The Metro Rail Guy!
– TMRG
How many launching gantry are going to be there.
If gantries there im interested
Sir,do u have requirement of civil engineer ??
Sir,do u have requirement of civil engineer ?? If u have then pls contact me at 9675150283
Sir do you have any requirement of civil contractor ? If you have then contact me at 9818307570
Sir do u need any official employee.
I need a job pls contact me 9868908401