IRCON Wins Delhi – Meerut RRTS’ Electrification Package 19

November 24 Update: IRCON has been awarded the line’s electrification contract with a value of Rs. 723 crore

October 24 Original Post:

Indian government-owned IRCON International Ltd. on Friday evening emerged as the lowest bidder for the 82.15 km Delhi – Meerut RRTS Line‘s Package 19 involving 25kV AC overhead equipment (OHE) electrical supply works, after officials from the National Capital Region Transport Corporation (NCRTC) opened financial bids submitted by different firms.

NCRTC invited bids in January from firms in 2 lots (sub-packages) – the first from Sarai Kale Khan to Duhai EPE and the second from Duhai EPE to Modipuram. They opened technical bids in June to reveal 7 firms had submitted a total of 11 bids. During technical bid evaluation, Tata Project’s bid for Lot-1 and Linxon’s bid for Lot-2 were rejected and as such their financial (price) bids were not opened.

NCRTC’s estimate for both lots is unknown. I’ll add it in here when available.

Package 19 – Lot 1

Financial Bid Values:

FirmBid
IRCON International Ltd.Rs 317.80 cr
Sterling & Wilson Pvt. Ltd. – STS JVRs 325.93 cr
Siemens Ltd. – KEC International Ltd. JVRs 347.43 cr
Larsen & Toubro Ltd. (L&T)Rs 405.00 cr

Scope of Lot-1: Design, Supply, Installation, Testing and Commissioning of Receiving Sub Stations [including 25 kV AC Traction cum 33 kV Auxiliary Main Sub Stations], Extra High Voltage & High Voltage Cabling, 25 KV Overhead Equipment (FOCS/ROCS), Auxiliary Power Supply [including
Auxiliary Sub Stations], Operation Control Centre and Associated Works on Viaduct & Tunnel from Sarai Kale Khan to Duhai (EPE) [including Jangpura Stabling Yard and Duhai Depot] and SCADA System for Complete Corridor of Delhi–Ghaziabad–Meerut RRTS Corridor of NCRTC

Package 19 – Lot 2

Financial Bid Values:

FirmBid
IRCON International Ltd.Rs 404.94 cr
Siemens Ltd. – KEC International Ltd. JVRs 441.27 cr
Sterling & Wilson – STS JVRs 443.27 cr
Larsen & Toubro Ltd. (L&T)Rs 535.00 cr
Alstom Transport India Ltd.Rs 750.87 cr

Scope of Lot-2: Design, Supply, Installation, Testing and Commissioning of Receiving Sub Stations [including 25 kV AC Traction cum 33 KV Auxiliary Main Sub Stations], Extra High Voltage & High Voltage cabling, 25 KV Overhead Equipment (FOCS/ROCS), Auxiliary Power Supply [including Auxiliary Sub Stations] and Associated works on Viaduct & tunnel from Duhai (EPE) to Modipuram [including Modipuram Depot] for Delhi–Ghaziabad–Meerut RRTS Corridor of NCRTC

Route Map of the RRTS Phase 1’s Lines – view Delhi – NCR RRTS info & full route map

If no issues arise during financial evaluation, then IRCON International will go on to be awarded with Package 19’s contract in the coming weeks. They will be required to complete all work – from design to supply to installation to testing to commissioning – in 1,523 and 1,642 days (approximately 4.5 years) respectively from the letter of award.

A list of all packages (civil & systems) and their status can be viewed here.

For more updates, check out the NCR RRTS section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

2 Responses to "IRCON Wins Delhi – Meerut RRTS’ Electrification Package 19"

  1. Kanishka says:

    4.5 years is too far off in the horizon. A 300-odd crore job and 4.5years!!…such tasks should get completed in flat 30month’s (2.5yrs) time…nothing more

    i do understand that work is executed in a particular sequence: civil works (viaduct) must get completed before the rails can be laid; OHE wiring is done after rails are laid.

    …still 4.5yrs is like giving too much slack, the whole idea behind project management is to commission the project as soon as possible. NCTRC project management team got to answer some tough questions..

    share your thoughts, TMRG..

    Reply
    • Vinod Kumar Aslia says:

      Dear K, the main event is complection, T&C of Viaduct. The lay down testing and commissioning of power cables and interface with other systems takes time and it’s time consuming. PSY in Viaduct is where SIL is involved, hence all situations are to be taken care specially in Viaduct.
      Always the power supply is at the end, taking care of ALARP principal on safety. Hence, the time allocated of 4.5 yrs is reliable for PSY system.
      The whole idea behind project management is not to complete project as soon as possible, but to commission the project successfully in a time manner taking care of all safety aspects into account.