13 Bidders for Delhi Dehradun Expressway Phase 1’s Package 1

13 construction firms have submitted bids to construct Package 1 of the 210 km Delhi – Dehradun Expressway‘s Phase 1 after National Highway Authority of India (NHAI) opened technical bids on June 4.

This 6 lane greenfield expressway is being developed in 4 phases. Back in December 2020, financial bids for its 32 km Phase 1 (Akshardham in Delhi to Eastern Peripheral Expressway) were opened in December 2020 to reveal Gammon India and Gayatri Projects as the lowest bidders for its two packages.

While Gayatri has started work on the 16.85 km Package 2 (Delhi/UP Border to EPE Junction), NHAI in April canceled and re-invited bids for the 14.75 km Package 1 (Akshardham to Delhi-UP Border).

Bidders

  • Apco Infratech
  • Dineshchandra R Agrawal (DRA) Infracon
  • Gawar Construction
  • GR Infraprojects
  • HG Infra Engineering
  • J Kumar Infraprojects
  • KCC Buildcon
  • Krishna Constructions
  • NKC Projects
  • Ranjit Buildcon
  • Sadbhav Engineering
  • Transrail Lighting
  • Welspun Enterprises

Brief Scope: Development of six lane access control greenfield highway of Delhi-Saharanpur-Dehradun EC under BMP from Design Chainage 0.000 (Aksardham NH-9 (old NH-24)) to Design Chainage 14.750 (Delhi-UP Border) in the state of Delhi (Package-1) on EPC mode

Delhi – Dehradun Expressway’s route via NHAI’s promo video – view project information

The bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for each package.

In related news, I hear Krishna Constructions is the lowest bidder for the 119 km Phase 2’s Packages 1 and 4 in Uttar Pradesh. Back in March, 26 firms had submitted 43 bids for it. If anyone has detailed financial results, drop a comment below or send me a message here.

Details on this expressway along with a list of all packages and their status can be viewed here.

For more updates, check out my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

4 Responses to "13 Bidders for Delhi Dehradun Expressway Phase 1’s Package 1"

  1. Ashish says:

    Hi sir did you get the bidders list of Bangalore metro’s pink line? Waiting for your post.

    Reply
  2. Priyesh says:

    Any update regarding Delhi-Loni section?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *