6 Bidders for Delhi Metro Phase 4’s Consultant Work
6 consortia have submitted Expression of Interest (EOI) applications to provide consultancy services (contract DCS-1B) for implementing Delhi Metro’s Phase 4 project.
This 65.1 km project is well under construction and includes 1 new line (23.62 km Silver Line: Aerocity-Tughlakabad) and the extension of the Magenta Line (28.92 km Janakpuri West – R.K.Ashram) and Pink Line (12.58 km Mukundpur – Maujpur).
Delhi Metro Rail Corporation (DMRC) had invited bids for this service in May-end with an unknown estimate and 1620 day contractual period.
If someone is aware of all members in each consortia, then please drop a comment below or send me a message using the contact page.
Bidders (lead bidders only):
- AYESA Ingenieria y Arquitectura, S.A.U
- DB Engineering and Consulting GmbH
- Egis Rail
- MM S.p.A
- Rina Consulting
- SYSTRA
Update: Here’s an unconfirmed consortia list:
- AYESA – BARSYL JV
- DB Engineering and Consulting GmbH
- Egis Rail – Padeco – Mott Macdonald JV
- MM S.p.A – SMEC – Hill JV
- Rina Consulting – TYPSA – Yuksel – Artelia JV
- SYSTRA – Nippon Koei – OCG – RITES JV
Name of EOI: Short Listing of Consultants for Consultancy Services for implementation of Delhi MRTS Project Phase-IV
Details from the tender document:
Scope
The role of the Consultant is mainly advisory capacity to DMRC in various areas for successful commissioning of complete MRTS-IV Project.
- Consultancy services shall be provided through expatriates and local experts. In certain areas, consultancy services shall be provided through local experts only.
- Field of services shall be Project Planning, Programming and monitoring, Civil Engineering, Design & Structure, Quality assurance in construction, signalling, Telecommunication, Automatic Fare Collection System, Track, Ventilation, Air Conditioning, BMS, Rolling Stock and Safety, Health & Environment.
- Entire consulting team shall be headed by a Team Leader. The general responsibility of Team Leader and Scope in other areas will be provided to the Shortlisted Consultants.
Method of Selection
- Contract DCS-1B shall be Quality and Cost Based Selection (QCBS) wherein Quality Cost ratio shall be 80:20.
- Financial proposals shall be opened of the consultants whose Technical Proposals are determined to be responsive to the key aspects of the RFP.
- 80% weightage for technical score obtained and 20% weightage for financial score shall be taken for evaluation.
For more updates, check out the Delhi Metro section or my Home Page!
– TMRG
Today, inspection has started on the Mysuru Rd-Kengeri (Reach-2) line
https://twitter.com/Lolita_TNIE/status/1420021718991704064
Just an internal inspection with BMRCL’s top management. CMRS inspection is pending.
Any update on the opening of dhansa bus stand and tirlokpuri stretch.
Waiting for official inauguration date to be announced
TMRG, Please post the details of consortium when you get any info?
Also, if possible can you share technical openings of Ahmedabad GC and GMRC-DPR?
Hi, just added an unconfirmed consortia list. Trying to get bidder list for Ahmedabad’s GEC and GMRC’s DPR work right now. It’s been challenge!
What is the status of metro towards bawana
Just a lot of talk, discussions and meetings. Nothing else.
What will happen about Conflict of Interest?? As most of the bidder are already doing Detail design of same phase 4 lines.
Didn’t see a clause on that, but will be interesting to see how this plays out. I think this is a reoccurring theme across all projects.
mahipalpur to gurgaon cyber city is badly needed because the distance is hardly 4 km, yet it receives massive traffic
Totally! Feel like commuters can benefit with a new line on NH8 between Mahipalpur and Manesar, preferably one with limited stops.
What is the progress report of Silver Line?
3 underground sections (DC-07, DC-08, DC-09) are under bidding right now.
1 elevated section (DC-04) is under construction between Sangam Vihar – Saket G-Block.
When this contract DCS-1B of Delhi Metro consuting will open ?
Don’t know, but at this time definitely not in 2021. Technical bid evaluation is still underway.
May I know when will be results out for this bid
Hello
Can you tell whether the design consultants for complete phase 4 have been finalised?
Still under evaluation since March