16 Bidders for Kanpur Lucknow Expressway’s Package 1
February 23, 2022 Update: PNC Infratech is lowest bidder – see details.
December 27, 2021 Original Post: 16 construction firms have submitted bids to build the 17.52 km Package 1 of the 62.7 km Kanpur – Lucknow Expressway (NE-6) project after the National Highways Authority of India (NHAI) opened technical bids.
This 6 lane access-controlled highway will be upgradeable to 8 lanes and connect Shaheed Path in Lucknow with Azad Chauraha near Kanpur’s Ganga Bridge. It will run parallel to NH27 and consist of a 3.375 km elevated portion between Amausi and Bani which lies under Package 1’s scope.
NHAI invited tenders for its construction under the Hybrid Annuity Mode (HAM) model in September 2021 with a 2.5 year deadline and Rs. 1675.18 crore estimate.
Bidders:
- APCO Infratech Pvt. Ltd.
- Ashoka Buildcon Pvt. Ltd.
- Brij Gopal Construction Co.
- Ceigall India Ltd.
- Dilip Buildcon Ltd.
- Dineshchandra R Agrawal Infracon Pvt. Ltd.
- DP Jain and Company Infrastructure Pvt. Ltd.
- Gawar Construction Ltd.
- GR Infraprojects Ltd.
- HG Infra Engineering Ltd.
- IRB Infrastructure Developers Ltd.
- Megha Engineering and Infrastructures Ltd.
- Montecarlo Ltd.
- PNC Infratech Ltd.
- Shankarnarayana Constructions Pvt. Ltd.
- Vishwa Samudra Engineering Pvt. Ltd.
Brief Scope: Construction of Six lane upgradable to Eight lane of Kanpur Lucknow Expressway including spur from Km 10+980 to Km 28+500 in the state of Uttar Pradesh on Hybrid Annuity mode under Bharatmala Pariyojana (Package-I)
India’s environment ministry hasn’t issued a NOC for the project’s construction due its alignment passing through forest land, so a minor realignment might take place where the expressway and Lucknow Ring Road intersect.
Anyhow, all 16 bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for this package.
Design details on the Lucknow-Kanpur Expressway along with a list of all packages and their status can be viewed here.
For more updates, check out the Expressway section or my Home Page!
– TMRG
Any information for package 2
Bids to be opened Dec 29!
Everything I know about it is documented here:
https://themetrorailguy.com/nhai-kanpur-lucknow-expressway-information-route-map-status/
Boss , Please update when bid open for PKG1 we all are waiting for this project
Will definitely write about it!
Hello
We provide all type of construction works for All contractors, companies ,
Work of …
Energy Dissipation chamber,Cross barrier,RE pannel,Aproch slab, boundary wall etc …
We are under-construction in Apco infratech Pvt Ltd on project of Delhi- vadodara express..
Regards
Haryana Traders
9991162468
That’s a lot of bids, nice
TMRG, you mention in the general description page of this expressway that package 1 is from 10.98 to 28.5 km and package 2 is from 28.5 to 73.7 km. Then how come is the expressway 73.7 km long? Shouldn’t it be about 62.7 (73.7-10.98) km long?
Great question and you’re likely right.
I’m not sure why it starts at chainage KM 10.980 and not at 0.00. Maybe NHAI has used old NH-27’s chainage as a baseline. Maybe they are considering to upgrade 0 to 10.980 km?
Here’s my understanding:
0 to 10.980: Old NH27 (won’t be upgraded to eway standards at the moment)
10.980 to 28.500: Old NH27 (Package 1; brownfield upgrade)
28.500 to 73.744: Greenfield alignment (Package 2)
Actually project is starting from Shaheed path (Can quote as a Inner Ring road) which is having chainage 10.98 (10.98 KM from Starting of NH27)
No plan for development of 0 to 10.98 as of now.
project is only 62 KM.
Cool, thanks! I’ve now updated length on this post and info page.
Land to abhi aquire ki nahi gyi hai kwl notice hi bheji gyi hai
Boss please Show the Vacancy deatiles
I don’t track vacancies. Recommend checking out LinkedIn or directly contacting the winner when announced.
Dear Team………….may you also mention the type of pavement ,wether if its PQC or Bitumen
Didn’t see details of that in the basic tender notice. Typically it’s not included.
Hi All,
We SARLAXE provide Toll Plaza Collection facilities & Parking where these services plays an essential role like-in; Expressways, Highways Tolls, Shopping Malls & Multiplex, Airports, Hospitals, Metro stations, Hotels, Mixed-use developments, etc. We customize service delivery to meet the specific needs of each Toll plaza collection & Parking facilities, intending to complement their existing ideals, business strategies, and sensitivities with our rich past experience.
Looking forward..
Rgds
Aharnish Rajeiv
VP- Bus. Development
Sarlaxe Services
Mobile – +91-9911661818
*******
Hi All,
We provide Mobile Radio communicaton solutions for National Highways and also RF link solutions for CCTV, VIDS, ATCC.
For MRCS and RF link solutions please contact us.
Dinesh Mishra
[email protected]
Mobile No. 9990027766
7701857656
Hello Sir
Contact for these all type of construction works
👇
Energy Dissipation chamber,Cross barrier,RE pannel,Aproch slab, boundary wall etc …
We are under-construction in Apco infratech Pvt Ltd on project of Delhi- vadodara express..
Regards
Haryana Traders
9991162468
bid opening date ???
Financial bid opening date is never announced. I’ll share results when I hear something!
Who wins final work contract…?
Financial bids haven’t been opened yet.
PNC awarded 1 and 2 Package Lucknow- kanpur expressway.
Finally PNC Infratech emerged as L1 for both the Packages and hopefully will receive LOA soon. As the News came, PNC shares jumped to 272.60 with increase of 11.22%.