14 construction firms have submitted a total of 20 bids for packages OD-7 and OD-8 of the 464 km Raipur – Visakhapatnam Economic Corridor (NH-130CD & EC-15), also known as Raipur – Vizag Expressway.

This new six-lane highway will have a few sections that are access-controlled with a greenfield alignment connecting the states of Chhattisgarh, Odisha and Andhra Pradesh.

Both these civil construction packages are within Odisha near the border with Andra Pradesh. Package OD-7 is just 4 km long connecting Baraja – Kandili, so I’m inclined to believe it has a viaduct or tunnel section. Package OD-8 is 22.533 km long and will connect Kandili – Tumbiguda.

National Highways Authority of India (NHAI) invited tenders for their construction in August with a 2 year deadline and Rs. 759.75 crore & Rs. 1327.18 crore estimates.

Bidders:

  • Adani Road Transport Ltd: OD-8 only
  • Bekem Infra Projects Pvt. Ltd: OD-7 only
  • CS Construction Company Pvt. Ltd
  • Dilip Buildcon Ltd: OD-7 only
  • Dineshchandra R Agrawal Infracon Pvt. Ltd
  • DP Jain and Company Infrastructure Pvt. Ltd: OD-7 only
  • G R Infraprojects Ltd
  • HG Infra Engineering Ltd
  • KMV Projects Ltd: OD-08 only
  • Max Infra (I) Ltd: OD-08 only
  • Megha Engineering and Infrastructures Ltd
  • NKC Projects Pvt. Ltd: OD-7 only
  • PNC Infratech Ltd
  • RR Constructions and Infrastructure India Pvt Ltd: OD-7 only

OD-7’s Scope: Development of Six Lane Baraja Kandili Section of NH-130 CD Road from km 338.500 to km 342.500 under Raipur-Visakhapatnam Economic Corridor in the state of Odisha on Hybrid Annuity Mode

OD-8’s Scope: Development of Six Lane Kandili Tumbigura Section of NH130CD Road from km 342.500 to km 365.033 under Raipur Visakhapatnam Economic Corridor in the state of Odisha on Hybrid Annuity Mode Pkg-OD8

Indicative location of OD-7 & OD-08’s route – view Raipur – Vizag EC’s Full Route Map

The bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for each package.

Details on the Raipur – Visakhapatnam Economic Corridor along with a list of all packages and their status can be viewed here. This week I added a new page with a list of all planned Economic Corridors in India – check it out here.

For more updates, check out the Expressway section or my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

21 Responses to "14 Bidders for Raipur – Vizag Expressway’s Packages OD-7 & OD-8"

  1. Jenish says:

    Why L&T is not bidding in road project like here and many other projects.

    Reply
    • ASHHAR RUMI RAZA says:

      Because LNT is not intended to bid in any other mode than EPC, since all the recent projects of NHAI are in Ham or BOT mode so LNT is not bidding for the same.

      Reply
    • Jitendra Kumar says:

      L&T is very poor company in india
      L&T eating payment of Contractor/Labour.
      L&T is going Black list in many indian project.

      Reply
    • KOUSHIK ROY says:

      THE SO CALLED SUB-CONTRACTORS OF L&T HAS NOW BECOME THE CONTRACTORS.
      ITS TUFF FOR L&T , NOW TO GET ROAD JOBS-THE L1 CONCEPT EXISTS IN INDIA

      Reply
  2. Abhishek Threja says:

    Nhai invited tender for Amas dharbhanga expressway in November. Any updates on that

    Reply
  3. Sudu says:

    Is it a fully access controlled expressway or a brownfield highway ?

    Reply
  4. Rahul kumar says:

    Hey bro aur bhi expressway hai jo under construction usko bhi apni list mein Shamil karo mein apko uske name de raha hoon. Jesai Bangalore–Mysore Infrastructure Corridor, Chennai Surat Expressway, Chambal Expressway, Buxar – Bhagalpur Expressway, Aurangabad-Darbhanga Expressway, Raxaul-Haldia Expressway, Gorakhpur – Siliguri Expressway, Pune-Bengaluru Expressway Abhi aur bhi hai list mein usko apni list mein daldo aur unka update dalo ok bro best of luck 👍

    Reply
  5. Ak says:

    Hi..Tmg, U can add bangalore satellite town new ring road as well.. I had mailed u detailed map of it last year. 2 packages have already been tendered out

    Reply
  6. Abhishek Threja says:

    Technical bids for Indore Kota expressway will open on 6th January. Keep a track on this expressway also.

    Reply
  7. APS Group says:

    any upcoming road projects in Odisha ?

    Reply
    • TMRG says:

      Yes – 2 big ones:

      Four laning with paved shoulders NH configuration under Bharatmala Scheme – Rameswar (near Tangi on NH-16) – Brahmagiri – Puri – Konark – Astarang – Naugaon – Paradip Port – Ratanpur (Package- BM/18)

      Construction of New 6-Lane (CRRR) from Kuspangi (near Gobindpur) (NH-42) to Tangi (NH-16) (Near Bandalo Toll Plaza), Package-II Green Field Alignment