CMRS Inspects Kochi Metro’s Phase 1A: Petta – SN Junction
Abhay Kumar Rai – the Commissioner of Metro Railway Safety (CMRS) from the Southern Railways on Saturday completed a 3-day final safety inspection of Kochi Metro Phase 1A project’s 1.78 km section between Petta – Vadakkekotta – S.N. Junction.
The CMRS led a 3 member team and inspected everything you can think of – the section’s viaduct, rails/tracks, third rail, elevators, escalators, fire fighting system, Alstom signaling & train-control system, control room and passenger facilities at Vadakkekotta and S.N. Junction stations.
This section was constructed by KEC-CCECC JV through a Rs. 299.87 crore contract awarded in October 2019 for Package KAC-2. Besides constructing the viaduct and 2 stations at Vadakkekotta & S.N. Junction, a new 2 lane bridge across Panamkutty River was also part of their scope.
Trial runs (testing) on this section started in February 2022 – see images and details.
Kochi Metro’s 3.94 km Phase 1 extension, comprising of Phase 1A & Phase 1B, is being directly executed by KMRL after the Delhi Metro Rail Corporation (DMRC) completed the 25 km Phase 1 (Aluva – Petta) and left the city in 2020.
The CMRS is expected to submit a conditional approval this week. When this section becomes operational in the coming weeks, Kochi Metro’s Aqua Line will become 26.78 km long with 24 elevated stations.
A further 1.163 km extension to Thrippunithura (Phase 1B) is under construction by KEC – VNC JV through a Rs. 162.98 crore contract (Package KAC-4) awarded in July 2020. I see that section becoming operational in Q4 2023.
For more updates, check out the Kochi section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.