IRCON Awarded Aizawl Bypass’ Twin Tunnel Contract in Mizoram
IRCON International on Saturday announced it was awarded a Rs. 630.66 crore contract for the construction of 2.5 km twin tunnels of the Aizawl Bypass project in Mizoram by India’s National Highways and Infrastructure Development Corporation (NHIDC).
This 2 lane twin tunnel project with a 2.1 km long approach road will built as part of Package-2 of the upcoming 34.5 km Aizawl Bypass project on national highway NH-6. This bypass will connect Sairang & Phaibawk villages and consist of 10 major bridges and 1 minor bridge.
The tunnel section’s construction was approved by the Central Government on January 4, 2024 with a total estimated cost of Rs. 1313.28 crore. Tunneling work will be done through the drilling & blasting method. Tunnel boring machines (TBMs) will not be deployed.
NHIDC had invited bids for Package 2’s construction in October 2023 with a Rs. 893.79 crore construction estimate and 36 month (3 year) deadline. Technical bids were opened in early February to reveal 17 bidders.
Five of those, including Hindustan Construction Company (HCC) surprisingly, were disqualified during evaluation. Financial bids of the qualified 12 bidders were opened on March 9 to reveal IRCON as the lowest bidder.
Disqualified Bidders (5)
- CS Construction Company
- HCC – AMR India JV
- Transrail Lighting – Altis Holding JV
- GVPR Engineers
- Gammon – Choudhary Power Projects JV
Financial Bid Values
Firm | Bid (Rs. Crore) |
IRCON International Ltd. | 630.66 |
Ram Kumar Contractor – Shinde Developers | 642.00 |
Bharat Constructions (India) – AzVirt JV | 649.00 |
Max Infra (I) Pvt. Ltd. | 719.40 |
Rithwik Projects – EVRASCON JV | 730.20 |
Airef Engineers Pvt. Ltd. | 737.36 |
Patel Engineering – Dhorajia Projects JV | 741.00 |
Dineshchandra R.Agrawal Infracon – Ukrhidroenergobud JV | 764.82 |
Rail Vikas Nigam Ltd. | 776.25 |
ABCI Infrastructures Pvt. Ltd. | 792.00 |
Anusha Projects – KMC Constructions JV | 819.00 |
Vishwa Samudra Engineering – Age Insaat Ve Ticaret Anonim Sirketi JV | 909.00 |
NHIDC’s Brief Scope: Construction of Twin Tube Uni-directional Aizawl Bypass Tunnel of 2.5 km and its approaches of 2.1 km from km 10.600 to km 15.200 (Package-2) on Sairang – Phaibawk section of NH-6 in the State of Mizoram on EPC Mode
Per the central government’s press release in January, the primary objectives of this bypass “encompass mitigating congestion within Aizawl city on NH-6, circumventing heavily built-up areas, reducing traffic congestion, and enhancing road safety within scity limits. The initiative aims to ensure uninterrupted traffic flow, free from city-related impediments, ultimately cutting the distance between Sairang to Phaibawk by 22 kilometers and diminishing travel time by 1.5 hours.“