Oriental Wins Chennai Peripheral Ring Road EPC-05’s Contract
Oriental Structural Engineers Pvt. Ltd. (OSE) was today declared as the lowest bidder to construct and maintain 9.7 km Package EPC-05 of the 132.87 km Chennai Peripheral Ring Road project by Tamil Nadu Road Development Company (TNRDC).
This 6 lane access controlled expressway with 4 service lanes will form Chennai’s 4th ring road and connect Ennore Port with NH16 (old NH5) at Thatchur. Package EPC-05 lies within 30.10 km Section III which connects Thiruvallur Bypass with Sriperumbudur on National Highway 48 (Old NH-4).
Section III’s construction will be financed by Asian Infrastructure Investment Bank (AIIB) through a USD 378 million loan and is divided into 3 EPC packages: EPC-03, EPC-04 and EPC-05. Within those, EPC-05 is the shortest and will connect Sengadu (chainage 68+200) to Sriperumbudur (chainage: 77+900).
TNRDC had invited bids for this package in November 2023 with a 36 month construction deadline. It’s estimate remains unconfirmed to me but might be Rs. 780 crore.
Technical bids were opened in January 2024 to reveal 3 bidders. Among those, the bid submitted by Ramalingam Construction Company Pvt. Ltd. (RCC) was found non-compliant to the tender’s conditions and was disqualified.
Financial Bid Values
Firm | Bid (Rs. Crore) |
Oriental Structural Engineers Pvt. Ltd. (OSE) | 963.27 |
Larsen and Toubro Ltd. (L&T) | 1138.60 |
Brief Scope: Formation of New Six lane road from Sengadu (Design Chainage: 68+200) to Sriperumbudur (Design Chainage: 77+900) with paved shoulders and two lane service road on both sides in Section-III of Chennai Peripheral Ring Road Project under Package-EPC 05 on Engineering, Procurement and Construction (EPC) Mode including maintenance for 7 years
TNRDC’s estimate remains unconfirmed to me, so I can’t provide an assessment on the chances of a contract getting issued to OSE. We’ll have to wait and see how this plays out.
The entire project is divided into 8 civil packages, with Tata Projects and L&T currently working on Section 1 & 2. See a list of all packages and their status over here.
For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Get early-access to updates and support the site over here.
– TMRG
Hi, when section 5 work will be started. From sp koil to poonjeri. Please provide expected Bidding confirmation
hi this senthil