11 Bidders for Patna’s Bihta Airport’s Construction Contract
Eleven firms have submitted bids for the civil construction work of a new civil enclave at Bihta Air Force Station near Patna, Bihar after Airports Authority of India (AAI) opened technical bids on Friday.
Bihta Airport was approved by the Indian government’s Cabinet Committee on Economic Affairs in August 2024 with a total estimated cost of Rs.1413 crore. This new civil enclave at the Indian Air Force (IAF)’s base (view on Google Maps) will serve as Patna’s second airport and is located roughly 18 kms, as the crow flies, from Jayprakash Narayan International Airport.
Bihta Airport project includes construction of a new integrated terminal building and utility building with a 6-lane elevated road connecting to national highway NH-922.
The new 2-storey passenger terminal will have a built-up space of 34,346 sqm. It will be equipped with 6 aerobridges, 64 check-in counters, 6 baggage belts and be capable to handling 3000 Peak Hour Passengers (PHP).
The project also includes the construction of an apron with 10 parking bays suitable for A321 / B737 / A320 type aircraft, and two link taxiways. The IAF base’s runway will also be extended from 8000 feet to 12,000 feet as part of a separate contract.
AAI had invited tenders for its civil construction contract in September 2024 with a Rs. 665.85 crore estimate and 730 day (2 year) completion deadline.
Bidders
- Ahluwalia Contracts (India) Ltd.
- Capacite Infraprojects Ltd.
- D E C Infrastructure and Projects India Pvt. Ltd.
- Deepak Builders and Engineers India Ltd.
- Harsh Constructions Pvt. Ltd.
- ITD Cementation India Ltd.
- Joint Stock Company Industrial Association Vozrozhdenie
- KMV Projects Ltd.
- KPC Projects Ltd.
- Shalimar Corp Ltd.
- Vascon Engineers Ltd.
AAI’s Brief Scope: Development of New Civil Enclave at Bihta SH Construction of New Integrated Terminal Building, Utility Building, Elevated Road etc on EPC mode
The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.
Here are a few renders from AAI’s tender documents:
And here’s the masterplan schematic and some design drawings via AAI’s tender documents:
As seen above there’s space for expanding the passenger terminal for doubling processing capacity to cater to one crore passengers per annum.
For more updates, check out the Airports section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Hey Metrorailguy, I noticed that your Bangalore Metro has not been update. Phase 3 has been approved by the Central Govt so it should lie under approved, however approved shows 0kms.
Thanks – I’ve now updated it!
Do you have any information if both TBMs of Kanpur metro corridor-1 are launched towards Jhakarkati station or not ?
Haven’t heard or read of that happening
Please share updates on Darbhanga airport too
Ahluwalia was lowest bidder in Feb 2024. Details & design:
https://themetrorailguy.com/2024/02/22/ahluwalia-wins-darbhanga-airports-new-terminal-contract/
Great, i am the part of this project. Kindly update final bid opening date of Bihta Airport Bihar.
Darbangha airport is with Ahluwalia.
When the Financial Bid is opening
any update on the project
Financial Bid opened and JSC is L1, with -32% below from estimated cost. Dear TMG guy, can u pls share why 3 bids got disqualified??