Bids Invited for Mumbai – Ahmedabad Bullet Train’s Signaling Contract S1

India’s National High Speed Rail Corporation Ltd. (NHSRCL) on Saturday invited bids for the signalling and telecommunication (S&T) system of 508.17 km Mumbai – Ahmedabad High Speed Rail (MAHSR Bullet Train) project.

The scope of this long-delayed crucial package S-1 includes end to end design, installation and commissioning works for India’s first high speed rail line which will connect Mumbai and Ahmedabad through 12 stations at an estimated cost of Rs. 1.1 lakh crore (US $15 billion).

S-1 package, as I understand, was originally planned by NHSRCL under Package EW-2, but a tender notice was never published likely because of the delay, which continues, in finalizing the system’s rolling stock contract.

The tender notice is very basic and doesn’t provide any information about the system’s specifications. NHSRCL requires a non disclosure agreement (NDA) to be signed for gathering more information and has set it as prequalification to bid for the contract.

Per NHSRCL’s April 2024 brochure, the line will use Digital Shinkansen – Automatic Train Control (DS-ATC) technology with a special braking mechanism to prevent collision and overrunning at stations.

However, per the Integral Coach Factory (ICF)’s tender notice for manufacturing two prototype train-sets, which was awarded to BEML in October 2024, the line will be equipped with European Train Control System (ETCS) Level 2 signaling system. The 82.15 km Delhi – Meerut RRTS Line is configured with Alstom’s ETCS solution and is the only rail system in India running it at this time.

S-1’s Tender Details

  • Completion Deadline: 2555 days (7 years)
  • Pre-bid Meeting: February 18 2025 at 11 am
  • Date & Time of Submission of Tender: March 26 at 3 pm
  • Date & Time of Opening of Tender: March 27 at 3:30 pm

IFB Number: Package No. MAHSR – S-1

Brief Scope: Design, Manufacture, Supply, Installation, Over all Integration, Testing Commissioning, and Comprehensive Maintenance, of Signalling & Train Control System, Telecommunication System, and Operation Control Center System on Mumbai Ahmedabad High-Speed Rail Project, India.

Representational only: Tokaido Shinkansen’s Torikai Depotin Osaka, Japan –Photo by TS Japan Rail

While things on the civil construction-side are steadily advancing throughout its alignment in Gujarat and now Maharashtra, this project is clearly delayed on the systems procurement front.

There’s still no clarity on who will supply E5 Shinkansen train-sets, if at all, whether Hitachi or Kawasaki Heavy Industries. The only thing that is certain at this time is that BEML is building two 8-coach train-sets to test and run up to speeds of 250 kmph.

For more updates, check out the High Speed Rail section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

14 Responses to "Bids Invited for Mumbai – Ahmedabad Bullet Train’s Signaling Contract S1"

  1. Saurabh says:

    7 yrs? Why so long? That’s even more than the civil construction timeline.

    Reply
    • TMRG says:

      There maybe some maintenance period included, but realistically that’s how long it will take to build-install systems-test-operationalize C1 & C2 underground sections within Mumbai MMR

      Reply
      • Saurabh says:

        So what’s your estimate on when we can see the 1st trains running at least in Gujarat?

        Reply
      • Akash says:

        Why so ?
        The pace at which civil construction is going, according to the deadline…civil construction would be complete by 2027 at worse…it should not take more than 1 year to complete signalling work.
        I believe it includes 3-4 years of maintenance

        Reply
    • James says:

      I think a 2027-end start for all of Gujarat section is possible with Japanese trains, since they’ll be lightly modified in Japan and brought to India so even if it takes another year or so to to finalize a Japanese rolling stock contract. It’s even possible that if it’s running late, they can modify existing older Japanese Shinkansen trains to meet the deadline

      Reply
  2. Harman says:

    What percatage of work is completed?

    Reply
  3. Arif says:

    Do you happen to know about the E-2 Package tender status? It is understood that S-1 superseded the E2 package. I believe S1 package will only be considered for Japanese manufacturing companies only

    Reply
  4. Aryan says:

    Bro you wanted the location of GAD-1441. GAD-1441 is near Surat District at Chainage 297 Km from Mumbai. GAD-1441 is being build to cross over the E-Way.

    Reply
  5. satish says:

    TMRG, when do you see entire MAHSR being operational?

    Reply
  6. Uday says:

    Do you think this project is doomed 😭!!??? The delayes happening!

    Reply