L&T’s Patna Metro TBM-2 Records Breakthrough at PMCH Station
Larsen & Toubro (L&T) last week celebrated their sixth tunnel breakthrough at PMCH Station for 30.91 km Patna Metro Phase 1 project’s 8 km underground Package PC-03 connecting Rajendra Nagar – Patna Junction Railway Station.
This major milestone on Patna Metro’s 14.05 km Line-2 (Patna Junction Railway Station – New ISBT) was recorded by TBM-2 (DZ1091) – a 6.65m diameter EPB machine manufactured by China Railway Construction Heavy Industry Co. Ltd. (CRCHI).
This was TBM DZ1091’s second assignment and involved building a 1068m tunnel for the up-line from Patna University to PMCH, which took 12 months to complete since its relaunch in July 2024.

Prior to this DZ1091 had built a 1494m tunnel, also for the up-line, from Moin-ul-Haq Station to Patna University Station in 12 months.

Delhi Metro Rail Corporation (DMRC) had awarded L&T with Patna Metro Phase 1 Package PC-03’s Rs. 1989 crore contract in December 2021 with a 42 month deadline.
PC-03 will connect a ramp near Rajendra Nagar with Patna Junction Railway Station through TBM bored twin tunnels and 6 underground stations at Akashvani (formerly Dak Bungalow), Gandhi Maidan, PMCH, Patna University, Moin Ul Haq Stadium and Rajendra Nagar.



L&T’s TBM-1 (DZ1090) working on the parallel down-line tunnel had arrived at PMCH Station in late June.
With this development, 6 / 10 tunnel breakthroughs for Package PC-03 have been recorded. TBM-1 (DZ1090) and TBM-2 (DZ1091) had completed building the 1494m Moin Ul Haq – University twin tunnels in mid-2024, while TBM-3 (likely DZ1169) and TBM-4 (likely DZ1170) completed building 1.7 km twin tunnels from Gandhi Maidan – Patna Junction in March this year.
TBM-3 has already started its initial drive from Moin Ul Haq to Rajendra Nagar, while TBM-4 is being readied for commissioning – both for their final assignments.
In case you missed it, Hindustan Construction Co. Ltd. (HCC) in June was declared as the lowest bidder for 16.86 km Line-1‘s 8 km underground section (packages PC-05 & PC-06) connecting Rukanpura Ramp and Mithapur Ramp – see details here. I don’t believe HCC has received LOAs yet.
For more updates, check out the Patna Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Leave a Reply
Want to join the discussion?Feel free to contribute!