Tata Projects Launches 1st Segment for Ahmedabad Metro’s Reach-2

This past weekend, workers from the Tata Projects Ltd – China Civil Engineering Construction Corporation (TPL – CCECC) JV launched their first 48 ton precast segment near Doordarshan Kendra for building the 8.21 km Thaltej Gam – West Ramp ‘Reach-2’ section of Ahmedabad Metro’s 20.737 km Line-1.

This construction milestone was accomplished by TPL-CCECC a little over 12 months after they won a Rs. 721 crore contract for constructing this section by the Metro-Link Express for Gandhinagar and Ahmedabad (MEGA) in January 2017. Piling work to build this section’s foundation began in May 2017 along Drive-in Road, and the first pier to support the line’s viaduct was cast in October. With this development, segment launching work has now commenced on all 4 legs or ‘reaches’ of the 39.259 km Phase 1 project.

Besides the elevated viaduct & crucial bridge over the Sabarmati River, the TPL-CCECC JV is responsible for constructing 7 stations at Thaltej Gam, Thaltej, Doordarshan Kendra, Gurukul, Gujarat University, Commerce Six Road and Stadium Circle –

Thaltej Gam – West Ramp section – view Ahmedabad Metro map & information

Images of the launching gantry being set-up in January –

Photo Copyright Anil Yadav & Mohit Revalia

LG erection team – Photo Copyright Anil Yadav & Mohit Revalia

Commencement of launching on February 17 –

Launch team – Photo Copyright Anil Yadav & Mohit Revalia

Photo Copyright Anil Yadav & Mohit Revalia

Photo Copyright Anil Yadav & Mohit Revalia

First 31m long completed span with 11 segments –

Photo Copyright Anil Yadav & Mohit Revalia

Photo Copyright Anil Yadav & Mohit Revalia

For more updates, check out the Ahmedabad section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

10 Responses to "Tata Projects Launches 1st Segment for Ahmedabad Metro’s Reach-2"

  1. pankaj says:

    How would you rate the speed of work by Tata comparing others?

    Reply
    • TMRG says:

      Each package’s challenges are different – in some cases the contractor has a somewhat clear right-of-way to start work, while in others a large quantity of utilities first need to be rehabilitated. In any case, here are some dates and numbers for a simple comparison –

      Reach-1 – J Kumar
      contract awarded: Feb 2015
      1st segment: Feb 2016 (1 year)

      Reach-2 – Tata
      contract awarded: Jan 2017
      1st segment: Feb 2018 (1 year 1 month)

      Reach-3 – IL&FS
      contract awarded: Nov 2015
      1st segment: Dec 2016 (1 year 1 month)

      Reach-4 – Ranjit
      contract awarded: Jan 2016
      1st segment: April 2017 (1 year 3 months)

      Reply
  2. Pankaj says:

    Anandiben Patel attended ground breaking ceremony of NS route on 18 Jan 2016.

    https://www.ndtv.com/ahmedabad-news/ahmedabad-gandhinagar-metro-to-be-completed-within-4-years-anandiben-patel-1266954

    How could have IL&FS launched first segment in Dec 2016. I guess you meant 2017.

    Reply
    • TMRG says:

      Nope, 2016. Contract to IL&FS was awarded in Nov 2015, ground breaking was in Jan 2016, and the 1st segment was launched in Dec 2016. Nothing outlandish or bizarre about this timeline.

      Reply
  3. Pratik patel says:

    One of route pass by my home (just 80-100m) and I must say, work is fast, it’s almost ready at my area, now they completing work of Metro stations at all points

    Reply
  4. utpal shah says:

    its strange to plan to do work in such narrow route from H.L. COMM. SIX ROAD TO STADIUM ROUTE. how without thinking they started barricade and in between cut out which are practically accident
    prone zone. its purely planners wrong manage without supervise or site visit. only 3 meter wide road and near interval opening of society s entrances. daily accident occures near Terrace apartment entrance.
    no concave glass at cut out either skew barricade so entry from opposite direction can easily pass. how can society visitor park their vehicale. even its next to impossible for fire brigade or emergency vehicle can move out. cut out near samved hospital is very crucial. small temple and barricade so close so difficult to pass.
    may be in next coming days society members will remove barricade and take strong action against barricade system and cutouts..Project can. be stop by near by society.

    Reply
  5. utpal shah says:

    really a disgusting planning to do work on service road of hardly 8 to 10 feet wide.

    Reply
  6. Shaikh Soeb says:

    please give latest update about MEGA

    Reply
  7. Devarsh Prajapati says:

    Please share the latest update about Ahmedabad Metro

    Reply