DMRC Begins DPR Work for Bodaki Extension of Noida Metro

Delhi Metro Rail Corporation has commenced work for the preparation of a Detailed Project Report (DPR) for a 3 km extension of Noida Metro’s Aqua Line from the Depot Station to Bodaki Railway Station of Chamrawali Bodaki Village.

To assist with the DPR’s preparation, the DMRC on June 18 invited bids for a holistic traffic and transportation study, with a last date to submit bids of July 1, 2020. I won’t be tracking its bidders or winner, but if you’re interested then just drop a comment below or shoot me a mail.

Greater Noida Authority on May 31, 2019 had approved the preparation of feasibility studies and subsequently DPRs for the Aqua Line’s Bodaki extension and for a new 15 km line from Sector 142 to Botanical Garden. Following that, Noida Metro Rail Corporation (NMRC) requested proposals from RITES and DMRC, and appointed DMRC in July 2019 based on their lower fees.

With the feasibility report prepared and seemingly approved, DMRC has now moved on to preparing the extension’s Detailed Project Report.

Here’s a map from the tender document which shows the extension in red in the bottom right corner with 2 stations at Junpat Village and Bodaki Railway Station. This is unfortunately the highest resolution size available.

Noida – Greater Noida Metro Map – Copyright: DMRC

I’ve mapped the extension below:

Depot Station to Bodaki Railway Station extension – view Noida Metro info & route map

Bodaki is on the northern corner of a new industrial township being developed on 345 hectares by the Integrated Industrial Township Greater Noida (IITGN) as part of the Delhi – Mumbai Industrial Corridor (DMIC)’s Dadri-Noida-Ghaziabad Investment Region.

This is also where a new Inter-State Bus Terminal (ISBT) and multi-modal logistics hub (freight village) is planned at the intersection of the Western Dedicated Freight Corridor (WDFC) to Mumbai and Eastern Dedicated Freight Corridor (EDFC) to Kolkata.

Some details from the tender document –

The Traffic & Transportation aspect of this work involves collection of socioeconomic, land use, traffic & travel data from secondary sources as well as conducting primary traffic & travel surveys. Scope can be divided into two segments:

  1. Up-dation of passenger forecasting of existing Noida Metro corridor (Aqua Line) from Noida Sector-51 to Depot Station and Noida City Center to Noida Electronic City.
  2. Up-dation of passenger forecasting of proposed Noida Metro Corridors from Noida Sector-71/51 to Greater Noida (Knowledge Park-V) and Botanical Garden to Noida Sector-142
  3. The second segment mainly comprises of traffic data collection for the proposed metro corridor for extension of Noida Metro Rail Corridor (Aqua Line) from Depot Station to Bodaki Railway Station and realistic assessment of traffic on the proposed network.

The consultant has to assess:

  • Baseline total and assigned traffic onto the system across horizon years
  • Metro ridership and passenger km across horizon years
  • PHPDT (peak sectional load) across horizon years
  • Corridor wise ridership across horizon years
  • Different station loadings (boarding, alighting numbers) across horizon years
  • Unidirectional station boarding and alighting in the peak hour giving sectional load in peak hour
  • Base network, traffic and travel characteristics amidst a multi model setup
  • The dynamics of traffic shift to the proposed system in wake of competing modes across horizon years
  • The V/C ratio of all the proposed corridors before & after metro system is in place

The study shall be based on analysis of:

  • Review of the existing travel pattern
  • Review of network usage pattern by different modes
  • Review of existing transport facilities (all competing modes)
  • Review of the zoning system
  • Network plan and the specified project corridor
  • Hourly classified volume counts
  • Origin Destination (O-D) matrices – consolidated and mode-wise
  • Existing public transport network and their specific movement along the project corridor
  • Competing transport modes
  • Average Trip Lengths for various categories of vehicles

For more updates, check out the Noida – Greater Noida section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

5 Responses to "DMRC Begins DPR Work for Bodaki Extension of Noida Metro"

  1. Raghav mehra says:

    Looking for job, I have 5yr experience in cashier and sales. Thanks

    Reply
  2. Taps says:

    Hi TMRG – there was supposed to be a Railway Over-bridge to be constructed on the Bodaki Rail line for access to Ansal Hi-Tech Sushant Megapolis. Is it approved and under-construction? Also will the metro station be located somewhere close to that development?

    Reply
    • TMRG says:

      Hi – no idea about either question. Location of station will only be revealed when they publish a tender notice. Long way to go for that.

      Reply
  3. pushpendra kumar says:

    plz any take any actions for metro route Boraki railway station to Depot station, This route only 3.0km

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *