Shivalaya Awarded Delhi – Mumbai Expressway JNPT Spur’s P16
️Shivalaya Construction Ltd. on October 29 was awarded a Rs. 1357.81 crore contract for Package 16 of the 1350 km Delhi – Mumbai Expressway (DME) project‘s JNPT Spur per the latest status report published by the National Highways Authority of India (NHAI).
This 26.8 km 8 lane section connects Amne to Bhoj as part of a 92 km greenfield access-controlled road skirting around Mumbai connecting Virar with Jawaharlal Nehru Port.
NHAI had invited tenders for Package 16’s construction (along with 15 & 14) back in January with a 2 year deadline. Technical bids were opened in July to reveal 13 bidders.
If someone has bid results or a copy of the LOA, then connect with me here and I can add them into the post.
Update: Here are the financial bid values of the the lowest 5 bidders opened on October 14
Firm | Bid (Rs. Crore) |
Shivalaya | 1357.81 |
Agroh | 1471.01 |
IRCON | 1530.06 |
GR Infra | 1597.96 |
HG Infra | 1612.42 |
Brief Scope: Construction of Eight lane access controlled Expressway from Km 43.000 to Km 69.800 (Amne to Bhoj Section-SPUR of Vadodara Mumbai Expressway) on Hybrid Annuity mode under Bharatmala Pariyojana (Phase II-Package XVI)]
The project’s feasibility report has a detailed description of its route with a list of interchanges, major and minor river bridges, including a 4.39 km tunnel through Matheran Eco-Sensitive Zone – a part of Package 17.
With this development, the first of 5 packages related to JNPT Spur has been awarded. I’m expecting basic ground work to start before the year ends.
Package (length) & Section | Contractor / Status |
Package 14 (17 km) – Km 3.000 to Km 20.200 | 12 Bids Received |
Package 15 (23 km) – Km 20.200 to Km 43.000 | 17 Bids Received |
Package 16 (27 km) – Km 43.000 to Km 69.700 | Awarded to Shivalaya Construction (this post!) |
Package 17 (10 km) – Km 69.700 to Km 79.780 | 18 Bids Received |
Package 18 (15 km) – Km 79.780 to Km 94.290 | DPR in Progress. Tender Notice Pending |
The entire Delhi – Mumbai expressway has been divided into 4 sections with a total of 52 tenders / packages – see a list and their status here.
For more updates, check out the Expressways section or my Home Page!
– TMRG
Hat-tip: CK
I think pkg 18 will be built by MSRDC not by NHAI. It is given in environment clearance report of pkg 17.
Yup, most likely
MSRDC is not contractor, they also will have to call Tender.
Dear parag g
NHAI सरकारी उपक्रम है जो कि रोड बनाता नही बनवाता है
आपने जिस कंपनी का उल्लेख किया है उसने यह टेंडर NHAI से लिया है।
बो कंपनी L 1 रही होगी इसलिए उसे टेंडर मिल गया।
और nhai ने टेंडर जारी किया था
Please post all Consultancy project details also.
Hi – I don’t track highway consultancy contracts. No plans right now.