Mumbai – Ahmedabad Bullet Train’s Bridge over NE-4 Completed by MGCPL

MG Contractors Pvt. Ltd. (MGCPL) this weekend completed building a 260 meter long balanced cantilever (CLC) bridge under Package P1(B) for the 508.17 km Mumbai – Ahmedabad High Speed Rail (MAHSR Bullet Train) project.

This 4-span PSC bridge (GAD-1441) at chainage KM 297.287 has been built over the under construction Delhi – Mumbai Expressway (National Expressway NE-4). The completion of this bridge marks the completion of all five prestressed concrete (PSC) bridges in Gujarat – see details at the bottom of the post.

The bridge’s site is located west of Kosamba in Surat District between Surat and Bharuch Bullet Train stations – view satellite imagery on Google Maps.

Its structure consists of 5 piers (297P01, 297P02, 297P03, 297P04, 297P05) and has a 50m + 80m + 80m + 50m span configuration.

Photo by NHSRCL

India’s National High Speed Rail Corporation Ltd. (NHSRCL) had awarded Package P1(B)’s Rs. 549 crore contract to MGCPL in 2021. Their scope includes building 4 PSC bridges and 7 steel truss bridges within Larsen & Toubro’s 237.1 km Package C4 (Vadodara – Zaroli village on MH/GJ border).

Indicative alignment of Package C4 from the Gujarat-Maharashtra border to Vadodara – view Mumbai Ahmedabad HSR info & route map
Photo by NHSRCL
Photo by NHSRCL

With this development, 4 PSC bridges and 2 open web girder (OWG) bridges have been completed on Package P1(B) which includes 11 bridges. Here’s a list in chronological order:

  • GAD-1134 (70m, 673 MT) – OWG over National Highway NH-53 near Surat in October 2023
  • GAD-11 (260m) – PSC bridge over National Highway NH-48 at Amadpore in August 2024
  • GAD-68 (100m, 1464 MT) – OWG over Bhilosa Switching Substation near Silvassa in August 2024
  • GAD-10 (210m) – PSC bridge over National Highway NH-48 at Sasodra (October 2024)
  • GAD-9 (210m) – PSC bridge over National Highway NH-48 at Vaghaldhara
  • GAD-1441 (260m) – PSC bridge over National Expressway NE-4 at Kosamba (this post!)

Overall, GAD-1441 is the 5th and final PSC bridge in Gujarat to be completed after GAD-11GAD-10, GAD-9 (all 3 over NH-48) and GAD-33 (over NH-64).

For more updates, check out the High Speed Rail section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *