L&T Launches Agra Metro Line-2’s 1st U-Girder at Agra Cantt
Larsen & Toubro (L&T) last Sunday night launched their first set of 2 U-girders for the construction of Agra Metro Phase 1 project’s 15.09 km Line-2 which will connect Agra Cantonment – Kalindi Vihar via 14 elevated stations.
This major milestone for Line-2’s construction, under Package AGCC-07, was recorded at piers P/18-P19 in Agra Cantonment using 27.90m long girders each weighing 155MT.
This event took place a little over four months from when L&T began pouring concrete to cast U-girders at their yard in Dauki village along Fatehabad Road. That development was a record in itself in India as they took just 2 months & 20 days to start casting activities.
Per L&T’s construction plan, they will cast 761 piers to build the line’s super-structure and launch 930 U-girders to form its viaduct.

Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded L&T with Package AGCC-07’s Rs. 1242.79 crore civil contract in November 2024 with a tight 24 month deadline.
Package AGCC-07’s scope includes the construction of the entire line’s viaduct, 14 elevated stations, 530m viaduct to Line-2’s Kalindi Vihar Depot, and interestingly a 2.61 km viaduct from north of Sadar Bazar metro station to Line-1’s PAC Depot built by Lisha Engineers as part of Package AGCC-03.

At Agra College Station users will be able to interchange and switch over to the city’s 14.25 km Line-1 (Sikandra – Taj East Gate) where an underground station is under construction by Afcons – SAM India JV as part of Package AGCC-02.



Long way to go but I’m excited to see how line shapes out and if L&T ends up breaking any other records (100th launch, 200th launch etc.).
For more updates, check out the Agra Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG