CMRL to Open 3 Sections of Chennai Metro in 2016

After opening a 10 km stretch from Koyambedu to Alandur in 2015, officials from the Chennai Metro Rail Ltd who recently interviewed with the Times of India revealed that 3 sections of the 2 metro lines are expected to open by August 2016! These 3 sections include:

Line 1: Section from Airport to Saidapet (10 km)
Line 2: Sections from Alandur to St. Thomas Mount (1.5 km) and Koyambedu to Nehru Park (8 km)

ChennaiMetroMap

Key sections to open in 2016 – view entire Chennai Metro map

Reminder: The 10 km Alandur – Koyambedu stretch opened for commercial operations on June 29 2015.

Line 1 – In October 2015, the CMRL had claimed to have started trials from the OTA station to Little Mount on the Airport-Saidapet stretch, but that turned out to be nothing more than a simple run to see if the tracks were fit for operation. Although track work is mostly complete, signalling & electrification works have only recently commenced and are expected to be completed by April.

Line 2 – In October 2015, the CMRL ran a OHE wagon from the Thirumangalam Ramp to Anna Nagar Tower station to again see if the tracks were fit for operation. Since then, the OHE wagon has made its way to Shenoy Nagar & back, but really has contributed nothing, and I mean nothing, towards the opening of the line’s underground section which has been completed between Thirumangalam ramp (north of Koyambedu) and Nehru Park.  As per CMRL, the Thirumangalam Ramp to Shenoy Nagar stretch will be electrified by the third week of this month and the Shenoy Nagar to Nehru Park section by May.

Now, as far as openings go, there are multiple variables at play which’ll determine when these sections will open up. These include how quickly track + signalling + electrification works can be completed, how quickly in-station interior works are completed (note: the St. Thomas Mount station is far from complete), how quickly the trials can be completed, how quickly the Commissioner of Metro Railway Safety (CMRS) conducts the requisite safety inspection & gives its approval, and lastly the availability of ministers to inaugurate the sections. So if you were to ask me, August 2016 seems a little too ambitious, but I do believe these sections will open by the end of the year.

For more updates on Chennai’s Metro, check out the Chennai section of the The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

7 Responses to "CMRL to Open 3 Sections of Chennai Metro in 2016"

  1. Harun says:

    Any updates on the construction between Adambakkam and St.Thomas mount station?

    Reply
    • Thangaraj says:

      Adambakkam and St.Thomas mount station not taken by CMRL.. its under IR and for past 2 years its under land acquisition problem.. it wont compete for atleast another 2 years time..

      Reply
  2. mani says:

    Sorry to disapoint 2016?

    Reply
  3. Shreedhar says:

    WHEN THIS CMRL will start functioning from Airport to Washermanpet(MINT) ??
    Any one can guess ?

    Reply
    • TMRG says:

      2018/19. Construction is on hold between May Day Park and DMS. New contract will be given by month end to complete tunneling work.

      Reply
  4. Shan says:

    when will the Metro starts functioning from Mint to saidapet?

    Reply
    • TMRG says:

      Looking at a 2018 opening. There are 2 tunnels pending between Thousand Lights and AG-DMS stations each 1.67 km long.

      Reply