MMRDA Approves Appointment of Contractors to Build Mumbai’s Metro

Hat tip to Raj B. Aklekar for sharing this news!

After NCC, Simplex & J Kumar were last week revealed on TMRG as the lowest bidders to build 3 packages of Mumbai Metro’s new 16.5 line from Andheri (East) to Dahisar (East), the Executive Committee of the Mumbai Metropolitan Region Development Authority (MMRDA) has now approved their appointments! Besides constructing the line’s elevated viaduct & 16 stations, the contractors would also be responsible for partly designing their sections by working together with the yet-to-be-appointed Detailed Design Consultant (DDC).

MMRDA

Press Release by MMRDA – Source: MMRDA

To sum it up:

• Package 1 – Simplex Infrastructure: Andheri (E) to New Ashok Nagar with 5 stations at Andheri (E), Shankarwadi, JVLR Junction, Mahanand and New Ashok Nagar.

• Package 2 – J Kumar Infraprojects: New Ashok Nagar to Mahindra & Mahindra with 6 stations at Aarey, Dindoshi, Pathan Wadi, Pushpa Park, Bandongri and Mahindra & Mahindra.

• Package 3 – NCC: Mahindra & Mahindra to Dahisar (E) with 5 stations at Megathane, Devipada, National Park, Ovaripada and Dahisar (E).

MumbaiMetroPackages

3 packages of Andheri (e) – Dahisar (e) line – view Mumbai Metro map & information

The line is estimated to cost Rs 6208 crores out of which the Asian Development Bank (ADB) is expected to provide a loan of about Rs. 2200 crores, representing roughly 36% of the total cost. In October 2015, PM Modi had laid this line’s foundation stone following which the MMRDA officially invited bids in December for its construction.

To recap from a previous post, this line’s depot thankfully doesn’t have any issues and will come up at the AAI’s Remote Receiving station in Dahisar along NH-8. Once the 3 work orders are issued, the 3 contractors will have 30 months (incl. the monsoon period as stipulated by the MMRDA) to build their respective sections. This would be Simplex Infra’s second metro related contract in Mumbai after they had previously won the bid & built the entire viaduct of the 11.4 km line 1 between Versova & Ghatkopar. Both J Kumar & NCC have ample experience and are currently building the first line of the neighboring Navi Mumbai’s metro from CBD Belapur to Pendhar.

As far as timing goes, I expect preparatory works for mapping en-route utilities and obtaining clearances for diverting traffic to begin in May – right before the monsoons begin their onslaught. Once the rains subside in August-September, piling rigs will be brought in to build the piers’ foundation to effectively kick-start the construction phase.

For more updates on Mumbai’s Metro, check out the Mumbai section of the Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

12 Responses to "MMRDA Approves Appointment of Contractors to Build Mumbai’s Metro"

  1. Sharadchandra says:

    Good News, after long time Mumbai is going to start construction of Metro.

    Reply
  2. Kandivali says:

    What about the superb traffic jam on western express highway? Where’s the space?

    Reply
  3. sam says:

    no news on Mumbai metro 3 they are sleeping

    Reply
    • TMRG says:

      Hi, they’re awaiting JICA’s final approval to award contracts now. As all the bid received for civil construction (tunnels+stations) were more than expected, they had to strip the contracts off of basic things. Recently they invited separate bids for the tunnel ventilation system and escalators.

      Reply
  4. Virender Thakur says:

    Long time… no news on Mumbai Metro Line 3

    Reply
  5. Kamal says:

    No update on likely start of activities on Dahisar (E) to Andheri (E) Metro..

    Reply
    • TMRG says:

      Hi, barricades for road widening & utility shifting have started appearing at different places. Construction work will only begin after the monsoons.

      Reply
  6. Kamal says:

    Thanks..I hv also seen couple of barricades of JKumar on Western Express Highway.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *