T-61 – 6th TBM for Mumbai Metro’s Line-3 Arrives at Mumbai Port
Parts of TBM T-61, a Ø6.68m dual-mode tunnel boring machine, made a touch-down at Mumbai Port this Sunday after getting shipped from Terratec’s plant in Guangzhou, China.
This Ø6.68m Earth Pressure Balance (EPB) machine passed factory acceptance testing (FAT) on September 21 and will be deployed by the J Kumar Infraprojects – China Railway Tunnel Group JV along with 2 other new dual mode rock TBMs (T-60, T-62) and 2 refurbished TBMs (S-63, S-64) to build twin tunnels on the line’s 4.94 km package UGC-05 (Dharavi Station – CSIA T1 TBM receiving shaft) and 4.45 km package UGC-06 (CSIA T1 Station – Marol Naka TBM receiving shaft).
As per the tunneling plan, T-61 will be deployed exclusively to build the 4687m down-line tunnel between Vidyanagari – Santa Cruz – CSIA T1 and Sahar Road –
Here’s a snap of Vidyanagari Station’s northern-end getting ready for deploying TBMs T-60 and T-61 –
With this development, 6 out of 17 TBMs are now in the city. Of those, TBM S-1073 was commissioned earlier this month while two TBMs are planned to be commissioned later this month –
• TBM T-58 at CST Station towards Kalbadevi Station on package UGC-02
• TBM S-1074 at Nayanagar Shaft towards Sitladevi Station on Package UGC-04
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
Why is the alignment curved between Santa Cruz & CSIA T1?
Couldn’t they go for a straight line alignment under the runway between these two stations?
Airports Authority of India under MoCA has a rule which prevents lines to be routed underneath runways. They’re fine with it passing underneath a taxiway though.
I believe a road tunnel passes under the Delhi Airport runways. If I remember correctly, it was constructed by DMRC.
It passes about 410m east of the runway. See satellite imagery –
https://www.google.com/maps/@28.5578478,77.1260042,768m/data=!3m1!1e3
CSIA T1 station could have been aligned near the Departure Gate, people will still need to walk around 300 m till airport.
Would have definitely been beneficial. Maybe space constraints, especially due to the ATC tower and road-network leading into and out of the airport, prevented them from choosing a closer site?
Now that they’ve selected that parking lot site in front of Taj Santacruz, it’ll be beneficial if they construct an underground walkway linking all terminals. If not, a shuttle service would help.
Please tell progress on THANE WADALA METRO route.
Thanks
MMRDA just re-invited bids for its construction:
https://themetrorailguy.com/2017/11/20/mmrda-re-invites-bids-for-mumbai-metros-line-4-and-line-2b/