Longjian–KEC Begins Casting U-Girders for Delhi Metro’s Phase 4
Longjian – KEC JV today began casting 28 meter long U-girders to build the elevated viaduct for a a 12.558 km extension of Delhi Metro’s Pink Line (Line-7), between Maujpur and Majlis Park, at their casting yard located near the Signature Bridge in Wazirabad.
Longjian – KEC JV was awarded Delhi Metro Phase 4’s second contract for Package DC-02 (Maujpur – Sonia Vihar – Majlis Park) in November 2019 with a contract value of Rs. 1,080 crore and completion period of 30 months.
Back in June, they resumed setting up their casting yard, commenced test piling work for a 560 meter cantilever bridge over the Yamuna River, and actual piling work for the main-line’s viaduct in Wazirabad.
Besides the viaduct, their scope of work includes building the line’s bridge over the Yamuna River, a 1.4 km PWD double-decker flyover between Yamuna Vihar and Bhajanpura, and 8 stations at Yamuna Vihar, Bhajanpura, Khajuri Khas, Sonia Vihar, Wazirabad Surghat, Jagatpur Village, Jharoda Majra and Burari.
DC-02 is the only package of the Pink Line’s extension in Phase 4. With this development, U-girder casting has commenced on 3 out of Phase 4’s 4 elevated packages:
- DC-01: 12.375 km (Vikaspuri Ramp – Haiderpur Badli Mor, Magenta Line) – Awarded to CCECC – KEC JV in November 2019. Casting began in July 2020.
- DC-02: 12.558 km (Maujpur – Majlis Park, Pink Link) – Awarded to Longjian – KEC JV in November 2019. Casting began today (this post).
- DC-03R: 7.473 km (Haiderpur Badli Mor – Ashok Vihar, Magenta Line) – Awarded to Sam India Builtwell – Gulermak JV in June in 2020. Casting yard is currently being setup.
- DC-04: 4.28 km (Sangam Vihar – Saket G Block, Aerocity – Tughlakabad Line) – Awarded to YFC Projects in December 2019. Casting began last week.
For more updates, check out the Delhi section of The Metro Rail Guy!
– TMRG
What is the status of 1KM patch near Mayur Vihar for Pink Line of DMRC?
Civil contract was awarded last year. Google Earth sat. imagery from March shows they’ve cleared out a portion of its path.
Satellite imagery:
https://twitter.com/TheMetroRailGuy/status/1273674909034700802
Rusted Reinforcement? how can they even allow the casting. DMRC is sleeping or what?
Hi TMRG-
Are Neb Sarai and IGNOU still a part of Aerocity-Tughlakabad line? Some say it is and some dont. Whats the truth.
My understanding is the from Saket G Block the next station is Saket and then Lado Sarai bypassing the Neb Sarai and IGNOU as indicated earlier. is it true?
It’s supposed to go down to the IGNOU area. I’m not aware of any further changes. See the map here with what I believe is current: https://themetrorailguy.com/delhi-metro-phase-4-information-map/