ITD Cem Casts Kolkata Metro Airport Station’s Top Slab

Workers from ITD Cementation India on Tuesday completed casting the top slab of Kolkata’s Biman Bandar (Airport) Station which will serve the city’s 6.87 km Line-4 (Noapara – Airport) and 29.87 km Line-6 (New Garia – Airport) in the future.

ITD was awarded this station’s Rs. 315 crore contract by Rail Vikas Nigam Limited (RVNL) in 2017 after they emerged as its lowest bidder, narrowly beating Tata Projects.

Route of Line-4 and Line-6 meeting at Netaji Subhas Chandra Bose International Airport – view Kolkata Metro info & route map

Casting works for this massive new underground station, with 4 lines and a train stabling facility, started on Monday (December 7) morning and ended after 30 hours of continuous pouring of 1730 cubic metre concrete with the help of 20 concrete mixtures.

Photo Copyright: Kolkata Metro
Photo Copyright: Kolkata Metro

Besides this, workers on December 8 also lowered the final rebar cage (18m × 5m × 1m) for casting the diaphragm wall of a pedestrian subway which will connect the station with Jessore Road and the Airport’s Terminal. Following that, 90 cubic metre of concrete was used to complete concreting works.

Photo Copyright: Kolkata Metro

For more updates, check out the Kolkata section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

11 Responses to "ITD Cem Casts Kolkata Metro Airport Station’s Top Slab"

  1. Dd says:

    Kolkata me new line konsi khulegi.
    Current status of line 3,4,5,6 or more any?

    Reply
    • TMRG says:

      Line-1’s 4.11 km extension to Dakshineshwar should open up in Q2 2021. Trial runs are going to start anytime now.

      Line-5 is dead. Rest are in various stages of construction with openings expected from 2023 onwards.

      Reply
      • U says:

        Kolkata Metro Line 2 will open in 2022 probably

        Reply
        • TMRG says:

          1 tunnel is pending and 2 TBMs need to be pulled out from the mid-shaft, as you might know. Both these steps should be completed by the end of 2021.

          Rest of the steps (system installation, testing, inspection, finishing works) will easily push the line’s opening to 2023. It’s going to be interesting to see how this all plays out 🙂

          Reply
      • Avijit das says:

        Any chance to do with Line 5 Metro Kalyani Expressway ???

        Reply
        • TMRG says:

          Not sure I understand the question. You mean, any chance of Line 5 being built on Kalyani Expressway instead? They explored possibility of it in 2018. Haven’t heard anything since then.

          Reply
  2. Rupraj Sengupta says:

    This line is being built by Kolkata metro from metro rail bhavan on park street not rvnl so design won’t be anything to write home about!

    Reply
  3. Sumit says:

    Is there any provision for vehicle parking near airport metro

    Reply
  4. Anujit says:

    Any update on Joka Metro?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Anujit Cancel reply

Your email address will not be published. Required fields are marked *