Segment Launching Begins for Pune Metro over Mula-Mutha River

Late last night, workers from J Kumar Infraprojects began launching precast segments at the southern bank of the Mula-Mutha River for constructing Pune Metro’s 14.665 km Line-2 which will connect Vanaz and Ramwadi through 16 stations.

This section of Pune Metro Phase 1 project’s Reach 3 over the river at Bund Garden is roughly 310 meters long and comprises of 10 piers. So far seven 9m wide segments have been launched for the southern-most span, with weights varying between 38 and 42 tons.

Construction for Reach 3 (Civil Court – Ramwadi)’s 7.578 km viaduct was awarded to J Kumar Infraprojects in August 2018 with a contract value of Rs. 388.58 crore. The 7 stations en route are being built by Afcons – SPCPL JV with a contract value of Rs. 470.43 crore at Mangalwar Peth, Pune Railway Station, Ruby Clinic, Bund Garden, Yerawada, Kalyani Nagar and Ramwadi.

Bridge’s location between Bund Garden & Yerwada – view Pune Metro Phase 1 route map & information

Workers began setting up their 66m long launching gantry with two 70 MT girders on December 14:

Pep talk in progress
LG getting erected on the southern bank
Ready to launch
Segment #1 going up at 1:30 am!
Morning view with #7 about to be hoisted – shot barely an hour ago

For more updates, check out the Pune section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

16 Responses to "Segment Launching Begins for Pune Metro over Mula-Mutha River"

  1. Mayank Rathi says:

    Hey TMRG, any updates regarding Agra metro? Are the contracts for other packages out?

    Reply
  2. Anonymous says:

    Good , one more step towards opening the line, What about the bridge at the western side near the railway station?

    Also, (bangalore mtero) Green line extension updates?

    Reply
    • TMRG says:

      No idea about the other bridge. Will need to check.

      Still waiting for BMRCL to release the launch date. Industry friends don’t have a rough timeframe either.

      Reply
  3. Anonymous says:

    Hey TMRG,
    you can make subreddit on Indian metro systems, people who regularly check your website will be happy to join it!

    Reply
    • TMRG says:

      Hey, that sounds nice but I don’t know if I’d be able to dedicate time towards it. My goal right now is to focus on the site and be consistent and timely 🙂

      Reply
  4. Parag Arjunwadkar says:

    Hi,

    When is the work planned to start and finish for vanaz metro to be extended to hinjewadi

    Reply
    • Peter says:

      Aren’t those two different lines?

      Reply
      • TMRG says:

        Yup. Although Vanaz and Hinjawadi are on the city’s west-side, I haven’t seen any plan to connect both places.

        Reply
        • PARAG YASHWANT ARJUNWADKAR says:

          thank you but i believe vanaz metro is planned to be extended till chandni chowk…any planned completion date on the same… i believe the same line will be extended to hinjewadi in phase-2…i read somewhere

          Reply
  5. ram chander says:

    Any update on warangal neo metro

    Reply
  6. Akshay kasar says:

    I fill the metro recruitment form bt when I ll do payment the show error window.

    Reply
  7. Loks says:

    Any updates on Ramwadi-Wagoli Extension??

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *