Sam-Gulermak Begins Casting U-Girders for Delhi Metro’s Phase 4

Sam India Builtwell – Gulermak JV on Tuesday night began casting 28 meter long U-girders to construct the elevated viaduct for a 7.473 km extension of Delhi Metro’s Magenta Line (Line-8) between Haiderpur Badli Mor and Ashok Vihar.

Sam India – Gulermak JV was awarded this section (Package DC-03R) of the Delhi Metro’s 65.1 km Phase 4 project in June 2020 with a contract value of Rs. 766.12 crore and completion period of 30 months.

In September 2020, this package became the 38.235 km Magenta Line’s third and penultimate package, where construction work has started, for its 28.92 km extension from Janakpuri West – RK Ashram.

Besides constructing this section’s viaduct viaduct, Sam India – Gulermak will build siding lines, a connection to the existing Mukundpur Depot, and 4 stations at Bhalswa, Majlis Park (interchange with Pink Line), Azadpur (interchange with Pink & Yellow lines) and Ashok Vihar. The line’s viaduct will also partly be integrated with a PWD flyover between Azadpur and Derawal Nagar on G.T. Road.

Route of Haiderpur Badli Mor – Ashok Vihar Section of Magenta Line – view Delhi Metro Phase 4 info & route map

Sam India – Gulermak started setting up their casting yard in Majlis Park back in July and commenced piling work for the main-line in September.

Casting Bay
First pour on Tuesday night around 9 PM

With this development, Sam – Gulermak JV has joined Phase 4’s three other elevated-work contractors in casting U-girders:

For more updates on India’s metro systems, check out my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "Sam-Gulermak Begins Casting U-Girders for Delhi Metro’s Phase 4"

  1. Clevin Gomes says:

    I think Mongolpuri Depot is now out of their plans, that’s why they using Mukundpur Depot.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *