KSM Wins Indore Metro Gandhi Nagar Depot’s Work
KSM Bashir Mohammad and Sons today emerged as the lowest bidder for the construction contract of Indore Metro Line-3’s Gandhi Nagar Depot (IN07) after Madhya Pradesh Metro Rail Corporation (MPMRC) opened financial bids.
This depot of Indore Metro’s Phase 1 project is the 4th civil package so far, and will be used to serve trains on the 33.53 km Yellow Line which will form a ring line around Indore city connecting Palasia – Railway Station – Rajwara- Airport – Bhawarsala via 30 elevated stations.
MPMRCL invited tenders for the depot’s construction in September 2021 with a 3 year completion deadline and Rs. 283.65 crore estimate to be funded through equity contribution from the Government of India and Government of Madhya Pradesh.
Technical bids were opened in November 2021 to reveal 16 bidders. During evaluation, bids from the following 10 firms were rejected as they were found non-compliant to the tender conditions.
- Altis Holding Corporation – Varindera Constructions (Altis-VCL) JV
- Amara Raja Infra Pvt Ltd
- Bansal Construction Works Private Limited
- Bridge and Roof Company India Ltd.
- Dhaya Maju Infrastructure (Asia) SDN Berhad
- Dineshchandra R Agrawal (DRA) Infracon Pvt. Ltd.
- Engineering Projects (India) Ltd.
- Shalimar Corp Ltd.
- SMS Ltd.
- Vijay Nirman Company Pvt Ltd
Financial Bid Values:
Firm | Bid (Rs. Crore) |
KSM Bashir Mohammad and Sons | 247.64 |
Quality Buildcon Pvt Ltd. | 255.64 |
IRCON International Ltd. | 293.91 |
Montecarlo Ltd. – Kunal Structure (MCL-KSIPL JV) | 300.35 |
URC Construction Pvt. Ltd. | 320.68 |
Suroj Buildcon Pvt. Ltd. | 353.27 |
Package: IN-07
Brief Scope: Construction of Rolling Stock Depot cum Workshop at Gandhi Nagar for Indore Metro Rail Project
Design details such as the number of stabling, workshop, inspection lines wasn’t mentioned in the basic tender notice and still remains unknown at this time. Altis-VCL recently won Chennai Metro Poonamallee Depot’s contract, so I’m curious to see why they got disqualified.
Anyhow, KSM Bashir Mohammad’s bid at Rs. 247.64 crore was well below MPMRCL’s estimate of Rs. 283.65 crore, so a contract should be awarded in the coming weeks. They recently wrapped up work at Kanpur Metro’s Polytechnic Depot in record time, so I hope to see some of that momentum getting carried forward at Indore as well.
Indore’s Gandhi Nagar Depot will initially house 25 train-sets of 3 coaches (total 75 coaches) as part of a larger 156 coach rolling stock contract, combined with Bhopal Metro, for which bidding is currently underway. Technical bids are planned to be opened on February 11, so stayed tuned.
For more updates, check out the Indore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Any update on when the bid for Bhopal metro’s Subhash nagar metro depot will open?
I’d give it another 2 weeks.
Technical bid evaluation is underway from 13 firms: https://themetrorailguy.com/2021/12/12/13-bidders-for-bhopal-metro-subhash-nagar-depots-work/
They can open soon in this month I feel so .
As the technical bids opened soon after Indore
What about Delhi Metro Phase 4 Rolling Stock tender, when it will be open
Currently scheduled for tomorrow! Technical bids i.e.
Nice update for Indore metro depot .
Bro if came to know the reason of why these companies were disqualified can you add that in this post .
Will the contract be awarded in this month and construction start on the depot till April ?
also how many segments are launched for Bullet train I didnt seen any update after the first segment was launched
Disqualification reasoning would be difficult to get – it’s quite subjective. Let’s see when the contract is awarded. I’ll have to check how many segments have been launched.
OK bro thanks
Bro can u give any contact details of KSM Bashir, as their website is not working and the number given in google , no one is picking up the call
Try LinkedIn: https://www.linkedin.com/company/k.s.m.-bashir-mohd.-and-sons/about/
Click on ‘See all 45 employees on LinkedIn’ to see profiles.
Request you to also inquire regarding Sabarmati Riverfront work where information is not free flowing
Isn’t the project complete? Or are you referring to various components like the pedestrian bridge & commercial developments?
who is the architect of Metro Gandhi Nagar park depot
No idea. Recommend reaching out to MPMRC.
Which Depots construction will complete first Gandhnagar Depot Indore or SubhashNagar Depot Bhopal.