16 Bidders for Bangalore Satellite Town Ring Road’s Package 2
16 firms have submitted bids to construct 20.9 km Phase 3 Package 2 of the 280.8 km Bangalore Satellite Town Ring Road (NH-948A) after National Highways Authority of India (NHAI) opened technical bids.
This 4-6 lane partially access-controlled under construction highway around Bangalore will have an alignment connecting 12 towns of Dobbasapete, Doddaballapura, Devanahalli, Sulibele, Hoskote, Sarjapura, Attibele, Anekal, Tattekere, Kanakapura, Ramanagara and Magadi.
It is being built in 3 parallel phases and involves construction of NH-948A and realignment of existing NH-648 (old NH-207). Phase 3’s Package 2 will connect Hoskote with the Karnataka – Tamil Nadu Border, just west of the city.
NHAI invited tenders for this package’s construction in December 2021 with a Rs. 530.89 crore estimate, 2 year deadline and 5 year maintenance period.
Bidders:
- Amar Infrastructure Ltd.
- Arcons Infrastructures and Constructions Pvt. Ltd.
- CDS Infra Projects Ltd.
- Dilip Buildcon Limited
- DP Jain and Company Infrastructure Pvt. Ltd.
- GVR Asiatrade Consortium Infra Ltd.
- Jandu Construction India Pvt. Ltd.
- Lakshmi Infrastructure And Developers India Pvt. Ltd.
- Lekcon Infrastructure Pvt. Ltd.
- PJB Engineers Pvt. Ltd.
- Ramalingam Construction Company Pvt. Ltd.
- S and P Infrastructure Developers Pvt. Ltd.
- Shri S.M. Autade Pvt. Ltd.
- SRC Infra Developers Pvt. Ltd.
- Varindera Constructions Ltd.
- VDB Projects Pvt Ltd.
Brief Scope: Construction of 4 lane realignment of Old NH 207 (New NH 648) from TN/KA Border (CH 0.000) to Hoskote (CH 20.900) under Bharatmala Pariyojana as a part of Bangalore Ring Road in Karnataka on EPC Mode.
The bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.
This under construction project has 9 packages. Design details and a list of all civil packages & their status can be viewed here.
For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Nhai could have saved costs by adding this package as a spur to BCE
Hope this package gets completed without any delay..once completed, truck traffic from Maharastra towards TN can take dobbaspet-hoskote-hosur route bypassing bangalore city.
Points project started date and earliest completion.and etc jobs machinery. Make as without delayed and split of into division right know without objection overrule and action make protection shelters machinery whose available works agreements completion of sketch road planned short time 24 *7 good news for all. Due the from basic amenities and perfect ion immediately act soon .request for consider.parking station all emergency .well planned without time discussion.
bro I have a question
What is the use of Ground supporting system which is placed between pillars before girder launching ..?
https://www.youtube.com/watch?v=oECy4XAiDaA
To support TBM launcher’s assembly
Looks good proposal and challenge is by when land acquisition start… Kanakapura is DK land, Doddaballapura/Devanahalli land under Gowdas family..
Land acquisition is going on…TN also should also speed up aquisition near hosur n forest clearance required in Bannerghatta
Any want to tack up package 2 work as L1. Contact me, 9513333156
Is the contract awarded to anyone? Do not see any announcement.
S&P Infrastructure Developers – Skylark Infra Engineering JV was lowest bidder ; contract status is unknown
https://themetrorailguy.com/2022/04/01/sp-siepl-wins-bangalore-satellite-town-ring-roads-package-2/
Is it not going through Chikka tirupathi and Hosur now ?