Montecarlo Wins Bangalore Satellite Town Ring Road’s Package 1

Montecarlo Ltd. (MCL) on Tuesday emerged as the lowest bidder to construct 35.766 km Phase 3 Package 1 of the 280.8 km Bangalore Satellite Town Ring Road (NH-948A) project.

This 4-6 lane partially access-controlled under construction highway around Bangalore will have an alignment connecting 12 towns of Dobbasapete, Doddaballapura, Devanahalli, Sulibele, Hoskote, Sarjapura, Attibele, Anekal, Tattekere, Kanakapura, Ramanagara and Magadi.

It is being built in 3 parallel phases and involves construction of NH-948A and realignment of existing NH-648 (old NH-207). Phase 3’s Package 1 lies entirely in Tamil Nadu and will connect Belagondapalli with the Karnataka – Tamil Nadu Border, south-east of the city.

National Highways Authority of India (NHAI) invited tenders for this package’s construction in December 2021 with a Rs. 998.73 crore estimate and 2 year deadline. Technical bids were opened on March 9 to reveal 6 bidders.

Financial Bid Values

FirmBid (Rs. crore)
Montecarlo Ltd.927
G R Infraprojects Ltd.1000
Dilip Buildcon Ltd.1048
Dineshchandra R Agrawal Infracon Pvt. Ltd.1199
Megha Engineering and Infrastructures Ltd.1212.26
KNR Constructions Ltd.1234

Brief Scope: Construction of STRR (West side) NH948A Balagondapalli (Tamil Nadu) to Karnataka or Tamil Nadu border from km 144.170 to km 179.936 in the state of Tamil Nadu on Hybrid Annuity Mode under Bharatmala Pariyojana

Belagondapalli – TN/KA border section is shown in red (HS-6) – Source:  Louis Berger’s feasibility report (view full route map)

MCL’s bid of Rs. 927 crore was well below Rs. 998.73 crore, so a contract should be awarded in the coming weeks.

I hear financial bids for Phase 3’s Package 2 (TN/KA Border (Km 0.000) to Hoskote (Km 20.900)) have also been opened. If someone has its results, leave a comment below or shoot me a mail here.

This under construction project has 9 packages. Design details and a list of all civil packages & their status can be viewed here.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

18 Responses to "Montecarlo Wins Bangalore Satellite Town Ring Road’s Package 1"

  1. indira says:

    Phase III starts from peddamadhagondapalli as per the documents on google, you have mentioned it has belagondapalli. which is correct.

    Reply
  2. Chetan says:

    I was told STRR would not be access controlled with accessibility they service roads throughout. But you say it is partially access controlled. Can you elaborate pls.

    Reply
  3. Prasanna lakshmi says:

    What is the package for land and when the project is going to take.

    Reply
  4. satyam says:

    This project is pqc and bitumine

    Reply
  5. Shekar Reddy says:

    Can I get the detailed map of the proposed road project

    Reply
  6. Nagesh says:

    Request to the project director STRR
    Sir , i have a 3 Escalators Hitachi need work .kindly contact 9600756758

    Reply
  7. Dr reddy says:

    The Tamilnadu stretch starts from Tamilnadu -Malur taluk border in North passing through hosur on eastern side and ending at tamilndu – (anekal taluk) karnataka border close to Belagondapalli

    Reply
  8. Dr reddy says:

    The Tamilnadu stretch starts from Tamilnadu -Malur taluk border in North passing through hosur on eastern side and ending at border of anekal taluk
    close to Belagondapalli

    Reply
  9. Dr reddy says:

    The Tamilnadu stretch starts from Malur taluk border in North passing through hosur on eastern side and ending at border of anekal taluk close to Belagondapalli

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Shekar Reddy Cancel reply

Your email address will not be published. Required fields are marked *