L&T Wins Chennai Metro Line-3’s Elevated OMR Section’s Work

Larsen & Toubro today emerged as the lowest bidder for constructing Chennai Metro Line-3’s first 10 km elevated package between Nehru Nagar – Sholinganallur after Chennai Metro Rail Ltd (CMRL) opened financial bids for package C3-CP08-EV-01/RT-01.

This is a retender of the 118.9 km Chennai Metro Phase 2‘s Package CP08-EV-01 which received 3 bids in July 2021. The tender got cancelled in December 2021 due to a major redesign of the line from a double-decker viaduct for vehicles and metro trains to separate parallel structures.

The scope of this corridor includes an approximately 10 km viaduct starting from a ramp south of Taramani Link Road Station with 10 stations on Old Mahabalipuram Road (OMR).

CMRL re-invited bids for its construction financed by Japan International Cooperation Agency (JICA) in December 2021 with a 36 month deadline and an unknown estimate. Technical bids were opened in February to reveal 6 bidders.

Tender No.: CMRL/CON/PHASE-II/CORRIDOR3/C3-CP08-EV-01/RT-01/2021

Financial Bid Values

FirmBid (Rs. Crore)
L&T1143.52
GR Infraprojects1211.59
JMC Projects India1252.47
NCC1285.60
HCC – KEC JV1288.54
DRA Infracon1592.08

Brief Scope: Construction of elevated viaduct (approximate length-10 km) including elevated ramp and ten (10) elevated metro stations at Nehru Nagar, Kandanchavadi Perungudi, Thoraipakkam, Mettukuppam, PTC Colony, Okkiyampet, Karapakkam, Okkiyam Thoraipakkam and Shalinganagallur

CMRL’s official Phase 2 map with my edits showcasing this package between Sholinganallur – Nehru Nagar – view Phase 2 info & route map

Like other Phase 2 packages, CMRL’s estimate for this is unknown, so I can’t provide an assessment on how L&T’s bid is placed and what the next steps look like.

Technical bids for the 10.13 km second and final elevated section of Line-3 (Sholinganallur Lake – SIPCOT 2) are currently scheduled to be opened on May 10. A list of all Phase 2 civil & system packages and their status can be viewed here.

For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

16 Responses to "L&T Wins Chennai Metro Line-3’s Elevated OMR Section’s Work"

  1. Krishna Mohan Rao A N says:

    Good CMRL

    Reply
  2. Samuel says:

    Oh again l&t!! That’s not surprising! But HCC KEC could have won cause they’re doing a great job!

    Reply
    • Anoop says:

      Why not L&T? Just asking out of curiosity being an L&Tite.

      Reply
      • Samuel says:

        As you see, for orange line 4, l&t and HCC KEC both started the work at the same time only, but within few months HCC KEC built numerous pillars and now they even started launching u girders. But l&t just now casted it’s pillars near saligramam and their work is too slow compared to HCC KEC. Even in red line 5, works are slower.

        Reply
  3. Pk says:

    Wow.. with just a 70crore diff L&T captured 1000crore project.. Others just 3 crore difference from each other..

    Reply
    • L KAMALAKSH RAO says:

      Why doubt?
      L&T is most reputed in infrastructure building and above all I am informed L&T does not entertain any bribery .
      This is a great point.
      They have the wherewithal to mange huge projects.

      Reply
  4. Katta says:

    L&T 👍Great Celebrate time

    Reply
  5. Rsankar says:

    Why they not give chances to other Indian companies.

    Reply
  6. ARAVINDRAJ C M says:

    Will we get any metro station for Tambaram route?

    Reply
  7. Janish says:

    The difference between L&T and the highest budder is 480 crores..just cant imagine how big the amount is.. best wishes to L&T on winning the bid

    Reply
  8. Bsr says:

    When’s the work expected to start in OMR? There’s no ground work happening here as part of corridor 3. However as part of corridor 5 work has started in perumbakkam and adjoining areas

    Reply
  9. Illanya says:

    How do you get this much detailed information?

    Reply
  10. Illanya says:

    Are you authorised to publish all these details?

    Reply
  11. AYYAPPAN says:

    Who win the tender of “CMRL/CON/PHASE-II/C3-ECV-01/RT-01/2022” , SHOLINGANALLUR LAKE-I,to SIRUSERI SIPCOT-2 with 9 nos Station cum viaduct for 10KM

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *