Ceigall Wins Ludhiana Bypass’ Construction Work

Ceigall India Ltd. is the lowest bidder (L1) to construct the 25.24 km Southern Ludhiana Bypass project in Punjab after National Highways Authority of India (NHAI) opened financial bids last week.

This 6 lane greenfield & access-controlled section of Ludhiana Ring Road will connect the 650 km under construction Delhi – Katra Expressway near Ballowal with the existing NH-44 (old NH-1) highway at Rajgarh.

NHAI considers this project to be a part of the Ludhiana – Ajmer Economic Corridor. They invited tenders for its construction in December 2021 with a 2 year deadline and Rs. 601.68 crore estimate. Technical bids were opened in April 2022 to reveal 4 bidders.

Financial Bid Values (courtesy Rishabh in the comments section):

FirmBid (Rs. crore)
Ceigall India702
Varindera Constructions768
Megha Engineering and Infrastructures811
GR Infraprojects851

Brief Scope: Construction of 6-lane GF Southern Ludhiana Byp from intersect. with NH-44near Village Rajgarh to intersect. with Delhi Katra Expressway (NE-5) near Village Ballowal km 00.000 – km25.240 as part of Ludhiana-Ajmer EC on HAM under BMP Phase-I in Punjab

The following map from the government’s bhoomirashi site shows the bypass’ alignment in blue color.

view large sized map

In addition to the Delhi – Katra Expressway, Ludhiana’s ring road will connect to the 75.4 km Ludhiana – Bathinda Expressway (NH-754AD) and 91 km Ludhiana – Rupnagar Expressway (NH-205K) for which civil contracts have been awarded.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "Ceigall Wins Ludhiana Bypass’ Construction Work"

  1. Rishabh Kumar Jain says:

    Bid result for Construction of 6-lane Greenfield Southern *Ludhiana Bypass from intersection with NH-44 near Village Rajgarh to intersection with Delhi Katra Expressway* as part of Ludhiana-Ajmer EC on HAM under BMP Phase-I in the state of Punjab.”

    Estimated Cost: 601.68
    Length: 25.24
    Client: NHAI
    DoS: 12-04-2022
    DoTO: 13-04-2022
    DoFO: 10-05-2022

    1. CEIGALL – 702/2.70/670.51 *L1*
    2. VARINDERA-768/2/724.01
    3. MEGHA- 811.76/2/764.13
    4. GRIL- 851/3.57/815.79

    Reply
    • TMRG says:

      Thanks! Have added them into the post

      Reply
    • ASHOK SHARMA says:

      HEARTIEST congratulations AND BEST WISHES to CEIGAL GROUP. I AM A SUB CONTRACTOR FROM LDH.FOR ELECTRICAL CROSSINGS UNDER THE THE ROADS. FOUNDATIONS. A D ERRECTION OF ELECTRICAL POSTS/ MASTS.DRAIN CONSTN.9478484926.ASHOK SHARMA.

      Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *