Quality Buildcon Wins 2 Delhi Metro Depots’ Expansion Work

August 24, 2022 Update: DMRC has issued LOA and awarded Quality Buildcon with a contract valued at Rs. 13,17,97,554.

June 14, 2022 Original Post: Quality Buildcon has emerged as the lowest bidder to supply and install pre-engineered buildings at Delhi Metro’s Shastri Park and Najafgarh Depots after the Delhi Metro Rail Corporation (DMRC) opened financial bids in May-end.

This work (Package CC-141R) is one of the low-value residue projects sanctioned under the 162 km Phase 3 project which is nearing completion.

Shastri Park Depot, among Delhi’s oldest depots, was built in Phase 1 and services the 34.69 km Red Line (Rithala – Shaheed Sthal). Najafgarh Depot was built in Phase 1 to service the 56.61 km Blue Line and was augmented in Phase 3 to service the new 5.15 km Grey Line (Dwarka – Dhansa Bus Stand).

DMRC invited tenders (bids) for this expansion work in December 2021 with an estimated cost of Rs. 14.16 crore and 9 month completion deadline. Technical bids were opened in February to reveal 13 bidders and financial bids were opened on May 25.

Financial Bid Values (Lowest 5)

FirmBid (Rs. Crore)
Quality Buildcon13.17
Pragati Construction14.39
E Pack Polymers14.79
Asha Enterprises14.99
Ghaziabad Mechfabs16.23

Brief Scope: Design, Fabrication, Supply and Erection of Pre-Engineered Steel Structure and Roofing for expansion of Workshop/other buildings at Shastri Park and Najafgarh Depots of Delhi MRTS project of Phase-III

Representational only (Mukundpur Depot) – Photo Copyright: DMRC

Quality Buildcon’s bid of Rs. 13.17 crore was well below DMRC’s estimate of Rs. 14.16 crore, so I see a contract getting awarded in the coming weeks without a lengthy financial bid evaluation period.

Technical bids for track-work (Package CT-42) within both depots are scheduled to be opened today (June 14). I’ll add an update here with a list of bidders instead of publishing a new post. Note the scope includes work inside the Blue Line’s Yamuna Bank Depot as well.

June 14 – 10 PM Update: DMRC has received 3 bids from:

  • Jai Durge Construction
  • Paras Railtech Pvt. Ltd.
  • Pee Mandal Projects Pvt. Ltd.

Scope of CT-42: SITC of Ballastless/Ballasted Track and Associated Civil Work in Shastri park Depot, Yamuna Bank Depot and Najafgarh Depot for augmentation of Additional Maintenance Facilities for Standard Gauge/Broad Gauge Corridor of Delhi MRTS Project of Phase-III

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *